What will you do, if your subordinate has a problem with
you? How will you deal with this situation
Answer Posted / yogesh
We agree to disagree. Healthy conflicts are always welcome
in the team, That provides way for idea generation and
innovation.
Most important is "LISTEN".
I faced similar situation in various projects.I respect the
vaious views and take the balance decision which helps the
team and over all project. Conflict resolution is mostly
depend on situations as well as leadership styles.
I always seen a gap between Intentions and interpretations.
There are always sensing sessions, formal , informal
meetings where in PM can anticipate the team dynamics and
team health.
Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
As a PMP, you will be required to comply with the Project Management Professional Code of Professional Conduct. This code refers to all of the following except: A. Reporting conflicts of interest B. Reporting experience and PMP status truthfully C. Complying with stakeholder requirements D. Complying with rules and policies of foreign countries
You've constructed the WBS for your recent project. Level two assignments have been made, and you've requested that the sub project manager’s report back to you in 3 weeks with each of their individual WBS constructed. All of the following are true except: A. The work package level facilitates resource assignments. B. The work package level is the lowest level in the WBS. C. The work package level defines the agreed-upon deliverables. D. The work package level facilitates cost and time estimates. ?
Your company, Kick That Ball Sports, has appointed you project manager for their new Cricket product line introduction. This is a national effort, and all the retail stores across the country need to have the new products on the shelves before the media advertising blitz begins. The product line involves three new products, some with multiple deliverables. You are ready to create the WBS. Which of the following is true? A. The WBS should include the three new products and the advertising campaign as level two deliverables. B. The WBS should include the three new products as level two deliverables. C. The WBS should include the three new products as level two deliverables and the advertising campaign as a level three deliverable. D. The WBS should include the three new products and the advertising campaign as level three deliverables.
Your hardware vendor left you voicemail saying that a potential snowstorm in the Midwest might prevent your equipment from arriving on time. She wanted to give you a heads-up and asked that you return the call. Which of the following is true? A. This is a secondary risk, which is an output of Risk Response Planning. B. This is a contingency plan, which is an output of Risk Response Planning. C. This is a risk, which is an output of Risk Identification. D. This is a trigger, which is an output of Risk Identification.
You are a project manager for Pizza Direct, which is a retail pizza delivery store. Your company is competing with another retail score for the option of opening two new stores in a foreign country. You know, but have not yet informed your company, that you are going to go to work for the competitor, which happens to be bidding for this same opportunity. What is the most appropriate response? A. You decline to participate in the initial meetings with the foreign business partners due to conflict of interest. B. You've not yet received an official offer from the competing company for your new job opportunity, so you choose to participate in the initial meetings with the foreign business partners. C. You decide to participate in the initial meetings with the foreign business partners because any information you gain now will help you when you make the move to the new company. D. You inform the foreign business partners that you're going to be working with a new company and that you know the deal they'll receive from the competing company is better than the one this company is proposing.
What are the initiation process outputs? A. Project charter, identification and assignment of project manager, constraints, and project overview documents B. Project charter, project overview, feasibility study, and constraints C. Project charter, identification and assignment of project manager, constraints, and assumptions D. Identification and assignment of project manager, project overview, constraints, and assumptions
You are the project manager for Lucky Stars nightclubs. They specialize in live country and western band performances. Your newest project is in the Planning process. You've published the scope statement and scope management plan. The document that describes who will receive copies of this information as well as future project information, how it should be distributed, and how the information should be stored and filed is which of the following? A. Scope management plan B. Communications management plan C. Information distribution plan D. Project charter
Your company provides answering services for several major catalog retailers. The number of calls coming into the service center per month has continued to increase over the past 18 months. The phone system is approaching the maximum load limits and needs to be upgraded. You've been assigned to head up the upgrade project. Based on the company's experience with the vendor who worked on the last phone upgrade project, you're confident they'll be able to assist you with this project as well. Which of the following is true? A. You’ve made an assumption about vendor availability and expertise. The project came about due to a business need. B. Vendor availability and expertise are constraints. The project came about due to a business need. C. You've made an assumption about vendor availability and expertise. The project came about due to a marketing demand. D. Vendor availability and expertise are constraints. The project came about due to a marketing demand.
What are the different types of software risks?
What are the tools for process improvement?
People are motivated by the need for achievement, power, or affiliation according to which theory? A. Expectancy theory B. Achievement theory C. Contingency theory D. Theory X
Obtaining formal project plan approval and sign-off is important for all of the following reasons except: A. Stakeholders are able to recommend a project Planning methodology to follow throughout the remaining process groups. B. Stakeholders are aware of the project details, which make them more likely to participate in future project decisions. C. Stakeholders will be more likely to cooperate. D. Stakeholders are aware of the specific details regarding project schedules, budgets, and risks.
What is the process in the Executing process group that determines if the project satisfies quality standards, identifies lessons learned, and review quality management activities to verify the correct quality elements are being examined? A. Quality Control B. Quality Monitoring and Control C. Quality Assurance D. Scope Verification
Lessons learned are used for all of the following except: A. To provide historical information that you can review during your next project B. To document employee performance C. To identify successes and failures on the project D. To record the causes of performance variances
Theory Y managers believe which of the following? A. That people are motivated only by money, power, or position B. That people will perform their best if they're given proper motivation and expectations C. That people are motivated to achieve a high level of competency D. That people are motivated by expectation of good outcomes