What will you do, if your subordinate has a problem with
you? How will you deal with this situation
Answer Posted / yogesh
We agree to disagree. Healthy conflicts are always welcome
in the team, That provides way for idea generation and
innovation.
Most important is "LISTEN".
I faced similar situation in various projects.I respect the
vaious views and take the balance decision which helps the
team and over all project. Conflict resolution is mostly
depend on situations as well as leadership styles.
I always seen a gap between Intentions and interpretations.
There are always sensing sessions, formal , informal
meetings where in PM can anticipate the team dynamics and
team health.
| Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
Your project is in the Scope Definition process. You've just completed the WBS. Which of the following is true? A. The WBS breaks the project deliverables down to a level where alternatives identification can be used to determine how level two assignments should be made. B. The WBS breaks the project deliverables down to a level where project constraints and assumptions can be easily identified. C. The WBS breaks the project deliverables down to the work package level where product analysis can be documented. D. The WBS breaks the project deliverables down to the work package level where cost and time estimates can be easily determined and quality control measurements can be determined.
Which of the following might require rebaselining of the cost baseline? A. Corrective action B. Revised cost estimates C. Updates to the cost management plan D. Budget updates
You are a project manager for Picture Shades, Inc. They manufacture window shades for hotel chains that have replicas of Renaissance-era paintings on the inside of the shades. Picture Shades is taking their product to the home market, and you're managing the new project. They will offer their products at retail stores as well as on their website. You're developing the project schedule for this undertaking and have determined the critical path. Which of the following is true? A. You calculated the most likely start date and most likely finish dates, float time, and weighted average estimates. B. You calculated the activity dependency, and the optimistic and pessimistic activity duration estimates. C. You calculated the early and late start dates, early and late finish dates, and float times for all activities. D. You calculated the optimistic, pessimistic, and most likely duration times and the float times for all activities.
Lessons learned are used for all of the following except: A. To provide historical information that you can review during your next project B. To document employee performance C. To identify successes and failures on the project D. To record the causes of performance variances
Your project sponsor has requested a cost estimate for the project you're working on. This project is similar in scope to a project you worked on last year. She would like to get the cost estimates as soon as possible. Accuracy is not her primary concern right now. She needs a ball park figure by tomorrow. You decide to use: A. Analogous estimating techniques B. Bottom-up estimating techniques C. Parametric modeling techniques D. Computerized modeling techniques
You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. The manager of the R&D department has agreed to release two resources to work on your project in order to meet the federal grant application date. This is an example of: A. Crashing B. Fast trucking C. Resource leveling D. Adjusting the resource calendar
What are the different project scheduling techniques?
During the opening rounds of contract negotiation, the other party uses a fait accompli lactic. Which of the following is true? A. One party agrees to accept the offer of the other party but secretly knows they will bring the issue hack up at a later time. B. One party claims the issue under discussion was documented and accepted as part of Scope Verification. C. One party claims the issue under discussion has already been decided and can't be changed. D. One party claims to accept the offer of the other party provided a contract change request is submitted describing the offer in detail.
Scope definition is necessary for all of the following reasons except: A. To subdivide project deliverables into smaller components B. To assess the stability of the project scope C. To facilitate time and cost estimates D. To facilitate responsibility and assignment
All of the following are true regarding configuration management except: A. Requires all acceptance decisions to be made through the CCB B. Serves as a change control system C. Describes the physical characteristics of the product of the project D. Controls changes to the characteristics of an item or system
The project charter: A. Includes a product description, describes the business need of the project, and is published by the project manager B. Includes a product description, describes the business need of the project, and is published by the project sponsor C. Includes the contract when the project is performed by a vendor and is published by a manager external to the project D. Includes a product description, describes the business need of the project, and is published by a manager external to the project
You are in the Planning process of your project, and your project sponsor has requested an accurate cost estimate in two weeks from today. You'll use which of the following techniques to provide her with the most accurate cost estimate? A. Bottom-up B. Analogous C. Top-down D. Earned value
Your company is going to introduce a new service called Phone Home. This service will allow you to speak the name of the person you want to call into your cellular phone. To call home, you would simply speak the word home into the phone, and it will dial that number for you. Your company is taking advantage of the progress that has been made recently with voice recognition software. Initial projections show that market demand is very high for this product. This project came about as a result of which of the following? A. Marketing demand B. Customer request C. Business need D. Technological advance
Explain the concept of total quality management.
Your project was just completed, accepted, and closed. As is customary for your organization, you conduct a post-implementation audit. The purpose of this audit includes all of the following except: A. Evaluating project goals and comparing them to project product B. Reviewing successes and failures C. Documenting the acceptance of the work results D. Documenting possible improvements for future projects