if water absorption is more than 25 percent in brick, what
is the defect in it?
Answer Posted / d v n potharaju
If the percentage of absorbtion exceeds 25% ,it indicates
that the brick is more porous and less in weight and could
not attain the required specific weight of 1920kg/mt3
| Is This Answer Correct ? | 13 Yes | 0 No |
Post New Answer View All Answers
Describe the advantages and disadvantages of using plastic and timber fenders?
What is the release of lien?
In an aggregate blending plant, water is sprayed before blending is performed. If the fine content in aggregate is as high as 25 %, will not the fines form into lumps / balls and distribution will not be uniform ? Further, the fines will stick onto the interior of pug mill and its content will be low. The mixed material is stockpiled for weeks / months before use. Will it not be better that blending is done in dry condition, and water will be added only during compaction at site. Please forward your comments and suggestions.
pls give me ans to ACT formula cube testing porpuse
What is the compressive strength of fly ash bricks?
Suppose you planning to paint newly fabricated workshop building made of structural steel of 10 tons total mass. How many litters paint primer for 1 coat and 2 coat of top coat?
In block work seawalls what is the purpose of slip joints?
03. a. The water cement ratio for achieving maximum strength of concrete is…… 1 b. Water/ cement is inversely proportional to-------------- 1 c. Increasing the slump decreases the strength: True / false 1
sir how can we find the cement and sand required for making 4" drop
Difference between lime, distemper and plastic emulsion?
Find out Cutting Length of Steel for Right angle Triangle? Where Opposite Side 4m, Adjacent side 6m. (Assume cover 40mm)
how much required strength of cement concrete bricks(size 230x115x75mm)
GIVE US DETAIL OF YOUR PRESENT EMPLOYMENT STATUS?
Explain the advantages and disadvantages of using plastic and timber fenders?
In the present situation of ban on mining sand from rivers,can we go for formation of earth dam filters viz;Horizantal sand blanket,inclined chimney and filters under rivetment with crushed rock sand of 6mm down size.If so what are the specifications and is there any codal provision for its authentication?