i have dry type transformers can you help me that how many
tests i can do to know the performence of transformer and
also please tell me about the BDV test and Insulation
resistance test in oil cooled transformers
Answer Posted / s ghosh thakur
The following tests to be done during commissioning.
1.Duster value.
2.PI test The value should be above2.o
3.Tan delta test.
4.Ratio test.
5.short ckt.impedance test.
6.vector test.
7.IR test.
8.Polarity test. Thats are sufficient.
BDV value of TRANS OIL should not be less than 50 kv.
IR value of oil cooled trans should be 100M w.r.t gr.and HT
to LT also 100M.PI test should carried out value min 1.5 to
2.0
Is This Answer Correct ? | 2 Yes | 1 No |
Post New Answer View All Answers
how does ELR works? explain
send me all basic electrical question and answers
I have 440v power coming to facility,( not being used ) can I buy large generator, (gas) to sell power back to electrical co.
defult setting in p220 micom motor proction relay for 11kv,640kw,f.l.a.-40a,1440rpm ht motor?
Electronic circuit
Why neutral is not used in three phases dol starter
Which power will flow first if we switch on a motor Active or Reactive? How?
How to select cable the size, what is the parameters use and what is the formulas use for this cable size calculation?
Is there possible to Test Transformer for Overfluxing Capability. Or is there any firm who does Overfluxing Test on Transformer?
what will be happen if earth point is being used for as a neutral point for raw power , and same will be used for ups earthing
in non technical way how can u define POWER FACTOR??
how can calculation ate Amps for cabel. Ex-for 1sqmm wire hou many amps we can draw
What is the range of the stator resistance of 3 phase induction motor?
Why the earth to phase voltage is high 250 compare to other two phases
What is the resonant peak?