I'm puting roof slab M20 Design Concrete,Twoway slab how
many days wait for remooving of shuttering?
Answer Posted / koti reddy allu
Hi Veeramani, it's Reddy here. First of all the basic
criteria for De shuttering is 1. Type of formwork i.e.
Vertical Form work for Columns, Soffit form work for
Slabs/Bems etc 2. The Effective Span of the member
Deshuttering period neither depends on Grade nor Depends on
Curing period according to IS 456 - 2000.
| Is This Answer Correct ? | 9 Yes | 1 No |
Post New Answer View All Answers
What is the Tor steel Consumption for residential building G+24 footing (thum rule) ?
List out some of the software program that can be useful for architect?
what is escalation?how it is done?
Define different types of roof systems?
What is the quantity of cement in mix m20 concrete?
how many kg cement & fine sand reqird in one sq meter 1:6 mortar ratio?
In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
How to measure the requirement of cement n sand for 12mm and 20mm plastering thanks in advance
how many running meters in one kilogram of 4mm pvc coated chainlink fencing
why building got air crack? if it get in one particular are what is means?
I have completed building maintenance course in mcvc stream .. can I apply for the post of " sthapstya abhiyantriki sahayyak"?
Which is the indian standard code of line out. ? How much tolerance fot 1 mt lenght? Its challenge....
Journal entry Gross salary 10000 Tax 1000 Employee contribution 2000 Employer contribution 2000
What is meant by cartesian coordinate system?
How to calculate the area of a irregular sized land in square feet?and what will be the total area of this land South-51.1ft , North-47.7ft , East-53.3ft , West-54ft ?please explain me how to calculate?