I'm puting roof slab M20 Design Concrete,Twoway slab how
many days wait for remooving of shuttering?
Answer Posted / koti reddy allu
Hi Veeramani, it's Reddy here. First of all the basic
criteria for De shuttering is 1. Type of formwork i.e.
Vertical Form work for Columns, Soffit form work for
Slabs/Bems etc 2. The Effective Span of the member
Deshuttering period neither depends on Grade nor Depends on
Curing period according to IS 456 - 2000.
| Is This Answer Correct ? | 9 Yes | 1 No |
Post New Answer View All Answers
Which purpose we use deck anchor in bridges?
How to calculate the quantity of cement mortar 2" for mosaic tile fixing 12"x12"?
What is the difference between engineering stress and true stress?
what is the amount of absorption of slurry in shuttering ply board. what is the amount of slurry leakage allowed for 1 m3 of concrete.
how much to get of BRC lapping in full yield and half yield ?
explain five benefits of using standard terminology in the measurement process?
Define What are the materials used in building a gravity dam?
what are the changes in concrete pour height as per IS 456, 2009?
1. For 10sq.m area(47 kg bitumen contain) of 45 mm thick bitumen mix layer..how much bitumen is required for 1600 sq.m and how much aggregate need for that ?? 2. And much tonnage of bitumen mix required for 10 sq.m area of 45 mm thick. Please give answer...
what is the proper procedure in conducting a california bearing ratio penetration test on soil on cbr machine?
What are the methods of measurement? Describe it shortly
What is dead load impact load live load
what is the formula to find the diagonal shape stirrups?
how much quantity of 1.5" nails and 2.5" nails are required for conventional formwork shuttering?
while doing the structural works of a simple ground+1 villa, can the columns be continued immediately after neck columns without tie beam, while the tie beam to be done after columns concreting.