I'm puting roof slab M20 Design Concrete,Twoway slab how
many days wait for remooving of shuttering?
Answer Posted / vinod
as per curing period will b 7days r 28 days the same can be
used for de shuttering
| Is This Answer Correct ? | 4 Yes | 4 No |
Post New Answer View All Answers
What is the diff between cad & cadd?
What is the FE 250 structural steel of 8mm tk plate testing sample intervals with IS code or international code?
The internal dimensions of a wire house 15m*5.6m and the maximum height of piles is 2.70m. What is the maximum number of bags to be stored in two piles ?
How you can turn off the display for dimension in CAD?
What is the material consumption- cement,sand,tiles etc for Toilet dado?
What is factor not to be taken in consideration in mix design?
i have span of 6m x 4m how do i calculate the reinforcement of steel i needed and to at what distance and also the thickness of slab. looking forward thank you RAVI
Describe the various methods of concrete curing?
for 16mm thick cement plastring 1:6 on 100 Sq.m.New brick work,the quantity of cement required is.
What is thumb rule in quality and quantity estimation of a Residential building??
please give me the rates of RCC(CUM), PCC(CUM), Brick Work(CUM), Tile Flooring, Saria Shuttering
Explain what are the phases inspections are done by local authority while construction?
What is meant by dimensioning?
can we make bricks using m10 grade cement concrete and what would be the ratio of raw materials used and price per brick ?
what does the track parameter mean in staad.pro?