Your Area is=27.87 Sqmt
Thickness is=0.012m
Total=27.87X0.012=0.33 Cum
25% of Dry Mix=25/100X0.33=0.0825 Cum
30% of Wet mix is=30/100X0.33=0.099 Cum
Total=0.33+0.0825+0.099=0.5115 Cum
If your Mix proption is 1:4 then you do
0.5115/(1+4)=0.1023
1 Part of cement is 0.1023X1=0.1023 Cum/0.035 Cum=2.92 Bags
Sand is 0.1023X4=0.4092 Cum=14.43 Cft
| Is This Answer Correct ? | 24 Yes | 4 No |
Post New Answer View All Answers
For plate load test why we are applying pressure 3 times the proposed allowable bearing pressure? Is there any supporting standards for this?
Elaborate advantages & disadvantages of using crusher dust instead of sand in rcc work.
What are the advantages of cad software?
How to calculate cement and river sand material Qty for waterproofing base coat and finish coat
satart to end steps by step process of building construction...? i want to planning theme accuretly
How much quantity of cement,sand,stone used to build 1 cum of cc road??
Is it necessary to apply tack coat over the primecoat. IF not what happens.answers other than 1.to superimpose the next layer(2) to adhere the layers so as to form homogenity.
what is the amount of absorption of slurry in shuttering ply board. what is the amount of slurry leakage allowed for 1 m3 of concrete.
How to calculate Volume of Wet cement concrete for a specific grade?
What is the difference between tor steel and tmt steel?
Sometimes the side of concrete bridges is observed to turn black in color. What is the reason for this phenomenon?
How many lbs are there in a yard?
afe or not
What is the mix propotion of M10,M15,M20,M25,M30,M40,M50.M60 cement content,aggrigate,sand and water ratio.
What is the effect of a building collapse?