plz give me the rate of RCC(1cuM), PCC(1 cuM), Brick Work
(1sqM)?
Answer Posted / vkg
cost of M30 (RMC) = [2700 + cost of cement]/cum
generally 1 cum contained 8 to 11 cement bags
| Is This Answer Correct ? | 29 Yes | 19 No |
Post New Answer View All Answers
significance of specific surface area of particles?
Currently my house construction is going on but we just realized that the portico earth beam couldn't connect with the original earth because the beam rod not extended so Please advice
explain what do you mean by the property development.
I need to constructive work in amaraj batteries
hii.plz send me hpcl placement papers for officers trainees for graduate engg plz my email id is ajm_knit@yahoo.com
1.what is the mix proportion for cement soil compressed earth blocks? 2.how to calculate the mix proportion for cement stablised earth soil blocks?
How much cement,sand,bricks and water needed for 1square metre brick work?
can i get civil engineering test papers.......?????
what post do you prefer to work in this company and why do you think you can serve better in such position?
Why should you consider yourself fit to be hired by jindal steel.
in a corner footing of a building, column lies in one corner. in this condition i want to know if the reactive pressure of soil will be uniformly distributed throughout the footing or will be uniformly varying as in the case of eccentrical loading.
What is a hatch patterns?
whats is difference between anchorage length and development length
I want to know the relevant IS codes of practice which deals with different testings of cement-sand mortar (nominal mix)that is being normally used for brick work or plaster work in the construction work.
Please let me know what is the simplest way of Calculating Mix Designs