Answer Posted / rabitha panat
As per IS:3495,the average water absorption shall not be
more than 20 persent by weight upto class 12.5 and 15
persent by weight for higher classes in 24hrs.Bricks,which
do not conform to this requirement shall be rejected.Over
or under burnt bricks are not acceptable for use in the
works.
| Is This Answer Correct ? | 17 Yes | 4 No |
Post New Answer View All Answers
Minimum and maximum size of the building components
five benefits of using standard terminology in the measurement process
Spider cracks occur in beam bottom due to––
while doing the structural works of a simple ground+1 villa, can the columns be continued immediately after neck columns without tie beam, while the tie beam to be done after columns concreting.
How do we calculate absolute pressure?
how many monpower required for 1 sqm normal RCC structure ( includes finishes & MEP )
how i can tak Quantity of mortar in block work
HOW MUCH STEEL REQUIRED FOR SLAB OF AREA 23'3"*18.3"? FOR SLAB HOW MUCH DIAMETER BAR WILL USE?
a concrete mix 1 2 4 by volume with water cement ratio as .6 by weight if moisture content in F.A is 6% with 20% BULKING AND IN C.A 1.5% by volume. find quantities of different materials required for one bag of cement
In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting?
Differentiate first angle & third angle projection?
will fix foundation bolts at site with out template is there any procedure?
What are the advantages of cad software’s?
Which ratio use for cement selery???
what is difference between fluidity and workability also how palsticizer works