in our sub station why we step down firstly 33kv\11kv then
11kv to 430v. can we direct step down 33v to 430.v.
Answer Posted / cv raman
Genarally load centers are very away from the Generating
stations & scattered too.No of 11/.430KV SS are very high
compared to 33/11KV SS. In the view of construction cost of
the 33/11KV SS is high compared to the 11/.430KV SS. At
this condition , construction cost of 33/0.420KV is very
high compared to the cost of 33/11KV SS. If we propose
33/0.420KV SS in all load centers the no. of ss will become
very high and construction cost will be very high.
Technically we can go for strigh step doun but it is not
economical.
| Is This Answer Correct ? | 16 Yes | 4 No |
Post New Answer View All Answers
why Current is lead 90 degree and voltage is lag 90 degree in a capacitor.? why Current is lag 90 degree and voltage is lead 90 degree in an inductor.?
What is the main cause of magnetism?
Will any motor burn if voltage provided is lesser than the rated voltage???? If yes, then how is speed control possible with voltage control
Who are the manufactures those manufacturing 3Cx2.5sqmm FRLS cables. I heard about FRLS technology adopted only in wires useful for wirings
after how many spot we must chang secondry cable in portable spot welding gun?
What is control system?
What is stepper motor. What is its uses?
Define peak overshoot.
How earthing/grounding done in aeroplanes and ships.
What is order of the system?
What is the pro & con of having 11kv & 33kv incoming, and what is the adv & disadv. of converting from 11kv to 33kv.
Why insulation level follows this order? transformer < bus bar < circuit breaker & Isolator < transmission line.
Whether 3 phase induction motorwith 100 hp capacity , Amp 160 for which sensitive earth fault relay , type CTUM 15 can be used?
what is a synchronizing lamp ?
What is conventional thermal current (Ith)