A floor has to be removed partially with block work tying
floors together, can block work continue on floor that has
to removed excluding demolishing works tying floor from
underside of slab and top of slab demolishing floor upon
completion?
Answer Posted / sujit
what is block working. if it is brick working or what.
if you want demolishing then you give support for others.
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
My daily concrete volume of M25 concrete is 1st day= 25 Cum 2nd Day = 45 Cum 3rd Day = 55 Cum 4th Day = 22 Cum 5th Day =72 Cum 7th Day = 49 Cum. What will be acceptance criteria of concrete considering as per is 456 cl.15 and table 11 (cl 16.1 and 16.3).
How to find coloumn vertical cut length floor to floor & lap + bend or anything plz clearfiy
I want to know how much the lapping length for the pilecap reinforcement.. we r using single pile cap which is 24mby54m and 2.5m depth.. total 91piles are supporting the pile cap.. how to do a steel reinforcement??
How to use of me trial wall plaster 6mm , 10mm par sqm. use in sand and cement ?
how can calculate cutting length of diamond ring
I want to know the material required per Square foot in rcc roof i.e.Steel ,Cement,
What Are The Steps Involved In The Concreting Process, Explain?
in levelling operation the first site on any change point is back site the second site on any change point is fore site the line commenses with fore sight & closes with backsight the line comensses with back sight & closes with fore sigh
i am laying a base of dimensions 6.5feet by 7feet by 1.25 feet depth how many bags of 25kg cement and how many bags of 25kg sand will i need
What are the responsibilities of a site manager?
Why should you show Client/Engineer activities clearly on the project plan?
What is Gsb tollens ?
to draw bm diagrams for portal frames under different loadings//
Formula for calculating the volume of bulb in underreamed pile
2. In a container filled with each of the following materials, at a porosity of 40%, determine the upward gradient required to cause the quick condition (a) Lead shot with a G = 13.75; (b) Fibre beads with G = 2.15; (c) Sand with a G = 2.32