Answer Posted / kcpatil

Single cycle plan is simple plan to execute the plan for a
particular equipment or subequipment on periodic basis and
also single cycle plan is may be performance-based or time-
based but here it not required to maintain strategy.By
entering main. category we will create maint. plan for
particular object by using t-code IP01

Is This Answer Correct ?    4 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Is it possible to change the equipment category once created?

480


What is purpose of serial numbers in sap pm module?

541


Differentiate between cost center and work center

458


Suppose there is a difference between the planned and actual hours of internal manpower where will you document the reason/ cause of this variance. Is there any standard sap facility available to address such situation.

596


What is preventive maintenance and key submodules under this?

555






What is the purpose of user status in notification? As a consultant what do you recommend to your client on the use of this facility?

562


What is purpose of technical id field in equipment master data?

495


What is the master data in sap pm?

563


What is the menu path for creating a user profile?

514


Where do you assign activity type in master data?

482


How many ways you can create a maintenance order in sap?

487


explain business completion?

501


What is purpose of construction type in equipment master?

502


Do we need to run this transaction code ip30 for all the maintenance plans which are scheduled on regularly daily basis or weekly basis so that if any scheduled object exists then it will get converted into the service order ?

648


What are difference type of planning are used in sap pm module?

451