WHAT IS THE %WASTAGES OF CEMENT, BRICK,TILES, STEEL,IN 1
M3,10M2,1 TON RESPECTIVELY
Answer Posted / navin baranwal
The permissible wastage for cement is 1%.For bricks
2.5%,For tiles, actually depends on the pattern laid but
taken 3-4% in general and for steel it is 3%.
| Is This Answer Correct ? | 44 Yes | 14 No |
Post New Answer View All Answers
how to calculate rate analysys of 1:6 plastering 10 sq m
Specific gravity of cement?
how to find ssm in foundation?
What is modular elasticity?
what radial pressure, the NP2 class rcc pipe can sustain?
How much cements bag (or in KG) required for 1 Sq. M concrete, for M-30 grad concrete as per CPWD and where is thr proof on site
how to calculate valuation for the old building?
How to calculate unit weight of concrete for m40 grade.
(Project Management Topic) What are the important criteria in the successful realization of the project?
what are the cube & Sylinder strength of concret M20,M25,M30,M35,M40,M60 ,M75,M10 ,M15
what"s the sort of beams?
how much shouid be the rate for ready mix concrete per cubic meter
One plate (women civil worker lifting Plate - Satti) sand measures how many cubic feet?
IS code for grade of concrete for bamboo lintel????
How to find permissible diagonal tensile stress in reinforced brick work