WHAT IS THE %WASTAGES OF CEMENT, BRICK,TILES, STEEL,IN 1
M3,10M2,1 TON RESPECTIVELY

Answer Posted / navin baranwal

The permissible wastage for cement is 1%.For bricks
2.5%,For tiles, actually depends on the pattern laid but
taken 3-4% in general and for steel it is 3%.

Is This Answer Correct ?    44 Yes 14 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what is cross hair cursor?

653


How much material will consume for following specification water tank (9*7.5*6 feet)?

1629


What is the difference between chamfer and fillet?

799


relation bet Coefficient consolidation Cv, time factor Tv, drainage path d, & time t is Cv=d2Tv/t Cv=d2t/Tv Cv=tTv/d2 Cv=Tv/td2

2403


What is GSB gradation

1897






What is the difference between pvc,cpvc and upvc and where it is used as per their properties?????

2362


How to make a c++ program that converts any base to base 10?

1625


Why should you consider yourself fit to be hired by jindal steel.

3935


acceptance criteria for concrete works

1693


what are the types of dimensioning?

1741


what"s the sort of beams?

1824


Explain what are the skills required to become an architect?

709


What is rate of concrete surface rendering work per sqm

1442


What are the RISKS during the project construction?

1742


what is right & short method of measurement of slab&beam

1650