Answer Posted / pratyush moha njha
column at corner of building will be bi axial.
column in a frame is uniaxial
| Is This Answer Correct ? | 31 Yes | 32 No |
Post New Answer View All Answers
what is the types of door's wood?
What is the meaning of soil reinforcement?
how to caliculate required amount of cement and sand required for 1cu.m.
how much required strength of cement concrete bricks(size 230x115x75mm)
how do you stabilize a waterlogged area in road construction
What is Gsb tollens ?
cause of cylinder test failure
Reinforced concrete: suppose you are doing rough estimate for purchase of rebar for reinforced concrete slab for single stores residential building. You know total concrete volume will be 100 m3. How many tons rebar 6, 10 and 12mm will you require for the project?
IS THERE ANY JOBS FOR THOSE WHO ARE IN FINAL YAER OF ENGINEERING(CIVIL) IN MUMBAI
What is Refuse Area In High Rise Building ?
A rock anchor 3 1/2” in diameter is placed in rock. The which has an allowable shear strength of 1200 psi. Determine the required anchorage length to safely carry a 80 ton load using a 2.0:1 F.S
How to calculate material and labor required for 100 m2 plaster?
What is meant by cad?
1) write Short notes about Shellow & Deep well? 2) What is the full form of SPT & SMB? write short notes. 3) write short notes about efficiency of Riveted joint.
In an aggregate blending plant, water is sprayed before blending is performed. If the fine content in aggregate is as high as 25 %, will not the fines form into lumps / balls and distribution will not be uniform ? Further, the fines will stick onto the interior of pug mill and its content will be low. The mixed material is stockpiled for weeks / months before use. Will it not be better that blending is done in dry condition, and water will be added only during compaction at site. Please forward your comments and suggestions.