What is the difference between a contract and a scheduling
agreement?
Answer Posted / jobin .j.singh
CONTRACT OUTLINE AGREEMENT
1.create the centrally contract(cross-plant) where you can
maintain different pricing for each & every plant.
2.you have to create release order w.r.t.outline agreement.
3.no detailed delivery schedule lines can be made in
release order.
4.no release documentation is created.
5.only time dependent conditions can be created.
6.some item category M or W can be use.
SCHEDULING AGREEMENT
1.plant location must be entered.
2.we do not have to create any other purchasing document
except for delivery schedule line.
3.delivery schedule lines items are created sub. to your
specific requirement.
4.can create both scheduling agreement with or without
release doc.
5.either time dependent or time independent conditions can
be created.
6.item category M or W can not be used.
| Is This Answer Correct ? | 23 Yes | 9 No |
Post New Answer View All Answers
You want to automatically convert purchase requisition to purchase order. How would you configure the system?
How is master data important in mm module?
What is an 'mrp area'?
What is the difference between purchase requisition and purchase order?
How many stock transport orders available in sap system. And how to configure stock transport orders?
What are the data in the mm module that are maintained at the company code level?
How will you consider un planned delivery cost in purchase?
State the importance of classification data?
How is the vendor created?
How does this impact an it user?
What is the lot size attribute of a material?
What is the difference between a purchase requisition and a purchase order?
What are the differences between company-owned special stocks and externally-owned special stocks?
Explain how you can change the standard price in the master material?
What is a batch?