what is the out turn of one masson in plastering, masonary
work in 8 hours, with limited healper?
what is the out turn of corpender in form work? wood work?
in 8 hour with limited healper?
what is the out turn of bar bendarin 8 hour with limited
healper for slabs, beams, coloumn?
Answer Posted / guest
10 SQM PER DAY ,1000 NOS DAY,
| Is This Answer Correct ? | 15 Yes | 7 No |
Post New Answer View All Answers
what will be the cost of thickness of 125mmor rcc measurement of 52x33.75 feet
How much cements bag (or in KG) required for 1 Sq. M concrete, for M-30 grad concrete as per CPWD and where is thr proof on site
what is the max. and mim. height of vertical post in informatry sign board which is used in highway projects.
What is the difference between routing maintenance and major maintenance in school facilities?
What is the likely strength of a 1:2:4 concrete mix?
what happening if we casting HV shunt reactor foundation pad at 50cm height different time (One day difference)
how meny typs of renging rod?
SAND AND STONE AGGREGATES WASTAGE PERCENTAGE IN CONCRETING WORK?
pls send me interview question paper with answer of EIL/AAI/UPSC/RPSC because i am doing prepration of compitation exam of UPSC for the Asst. Executive Engineer
What is meant by dimensioning?
How do we test on design and style in a software?
from one meter cube of stone masonry structure how much cubic meter of cement mortar we use as our estimation 25-30% is that correct for estimation of quantity of sand and cement(2:1) proportion of mortar
How do you convert wind speed into force?
what is the tensile strength of 10swg and 8swg gabion wire?
Explain the mechanism of cavitations in pipes and drains?