How to find quantity of cement mortar?
I want to know the req quantity of cement for plastering 300
sft in final coat with 12 mm. Any math involved? Plz help
Answer Posted / mukul chand
300 sft = 300*0.0924=27.72 sqm
Therefor wet vol. of mortar = 27.72 * 0.012 = 0.33264 cum
Increased by 20% for filling the depression etc.
= 0.33264 + 1/5 0.33264 = 0.4 cum (wet)
= 0.4 + 1/3 0.4 = 0.533 cum (dry)
Summation of proportion = 6+1 = 7 (1:6)
Therefor cement require = 0.533/7 = 0.761 cum.
Or 0.761 * 1440 = 109.71 kg.
| Is This Answer Correct ? | 34 Yes | 5 No |
Post New Answer View All Answers
WHAT IS THE CAUSES OF RUTTING ON FLEXIBLE PAVEMENT?
how to calculate labour strength for work for RCC,brickwork,blockwork,in &out plaster,flooring,dado,door frame & shutter,painting etc for constructing highrise building?
does a b.tech civil engineer fresher supposed to know how to design rcc structure?
for a column of size 400*230mm column reinforcement= 8-20x(cant write the symbol,i hope u guys undersstand,something like (fi) column stirups=8x@(4l) 230c/c 1)what does these mean 2)how to calculate quantity of steel for this column(ceiling height 11 ft)
Can anyone tell me the sequence of the activities in a drawing room, kitchen & Toilet including civil work, finishing, electrical & plumbing fittings
cement mortor 1:5 for 30 m2 12 mm tk plastering so how to calcualte its rate
I want to know how much the lapping length for the pilecap reinforcement.. we r using single pile cap which is 24mby54m and 2.5m depth.. total 91piles are supporting the pile cap.. how to do a steel reinforcement??
how to workable concrete cube test M-25 design mix
How to test cement,sand,20mmbluemetal,40mmbluemetal,bricks,concrete by visual and instrument
How can i display 5 asterisk and another 5 asterisk )?
Requirement of cement, and steel 1:2:4 ratio concrete in 1128 Sqft area(Cement No of bags, steel in Kgs)
What applicable rate of wct in bihar
how many kg cement & fine sand reqird in one sq meter 1:6 mortar ratio?
In cement making,what is meaning of blend,fineness,density.
why is M25 and Fe 500 assumed to be most economical? i feel it is not.This is because higher grade of concrete and steel has higher lapping length and anchorage length compared to lower grades..