Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How can we calculate the current if we have load in KVA and if
the load in KW then what formula will be use for calculating
the current. please give both the formula for calculating the
current.

Answer Posted / denzel101

For KVA rating, the formuler for current will be:

I = KVA/(0.707 x Voltage) for three phase system

For KW rating

I= KW/(0.707 x Voltage x cos phi)
for three phase system

Is This Answer Correct ?    5 Yes 17 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

in control panel, how can i measuring the distance between one bus bar to another bus bar. then now only for bus bar. in mpcb and contactor also. that means one mpcb to another mpcb how much distance? how can i calculate that.

2319


what is LSR?

2128


Why human body feel electric shock?

1012


where we use the SFU & FSU?

2359


7- What is the Dissipation Factor and the difference between it and Insulation Resistance Test? 8- What is the task (function) of DC and AC reactors in power plant? 9- What is the task (function) of (open delta with earthed) in some types in transformers? 10- What is the base of the selection of the vector group in transformers? 11- What is the zig-zag transformer and its function by drawing in large detail? 12- What is the polarity ? 13- Why we make short between phase(R) in high side and phase (r) in low side in vector group test? Where High Side ( R ,S and T ) and Low Side ( r ,s and t ). 14- What are the time on delay and time off delay? 15- What is the vector group? 15- What is the task (function) of different types of vector group such as Dyn11 , Dd0 , YNd1,……..,?

2215


How to calculate the current of Highpressure Mercury Vapour Lamp?what is the basis?whether we have to consider power factor or not?

2079


what is model question rrb junior engineer electrical gr.II

1891


What is shutdown of electrical sub station?

2438


hi pal, i am vengatesh from tamilnadu(chidambaram),i have called for the written test for the post of jr executive(ELECTRICAL) of AAI ,I dont know about the question paper pattern,so any kindly help me to face the examination,post me the model question papers and some tips to write my examination to (vengi.annadurai@gmail.com)

1833


what is the working principle of energy saver control panel. please give the complete calculation & theory.

2351


can u give me a brief idea about power line carrier communication ??

1913


Why in power plant projects we see DOL starting method used for motors upto 160 kW instead of star delta method

1775


how open delta PT works & what is its construction?

2178


How does the slip regulator works as a startor

1899


How to calculate that clean water supply in one Day from 150 KLD STP?

1938