A motor works on 30kw.it is working on 440volts.How much
amper will be Required?
Answer Posted / a.bala
Hai Ramya
The formula for I= KW/ 1.732x pf x Applied voltage in kv
So
KW =30
pf=0.8
Applied voltage = 440 v =440/1000=.440
30/ 1.732x0.8x.440=49.2 A
Is This Answer Correct ? | 7 Yes | 1 No |
Post New Answer View All Answers
Please give me a erda placement paper
7- What is the Dissipation Factor and the difference between it and Insulation Resistance Test? 8- What is the task (function) of DC and AC reactors in power plant? 9- What is the task (function) of (open delta with earthed) in some types in transformers? 10- What is the base of the selection of the vector group in transformers? 11- What is the zig-zag transformer and its function by drawing in large detail? 12- What is the polarity ? 13- Why we make short between phase(R) in high side and phase (r) in low side in vector group test? Where High Side ( R ,S and T ) and Low Side ( r ,s and t ). 14- What are the time on delay and time off delay? 15- What is the vector group? 15- What is the task (function) of different types of vector group such as Dyn11 , Dd0 , YNd1,……..,?
whati s the sludge current in ups
concept of busbar and load dispatching..?
What is the meaning of Insulation H for transformers????
How many size of cable required for a 300m long and 30kw inductive lode
Determine a suitable number of slors and conductors per slot for the starter 1 winding of a 3 phase, 3300 V. SO Hz 300 rpm alternator. The diameter is 2.3 m
What are the different sign conventions used in electric circuits?
if in 3-phase system voltage=440V,frequency=60Hz, current=400A. then if it is single phase then current=? and if it is single phasing then current=?
33kv Rated output avilable in market (any where in india)
What is the rating of circuit breaker needed for 300 KVA load in 33 KV supply line in a transformer of 33 KV / 415 Volt ?
what is the minimum recommended leakage current of an earthed cable connected to the body or skid of an alternator
as a electrical student why should i hire you?
how to calculate transformer load?
what is parellel power factor correction?