DG B-check,C-Check,D-check is depending upon the running
hrs.If the running hrs is not reached as mentioned.How to
conduct the DG checks.
Answer Posted / neeraj
DG check can also be done after completion of period like 3
months 6 month and 12 months
| Is This Answer Correct ? | 71 Yes | 23 No |
Post New Answer View All Answers
What are the uses of lead compensator?
why do we measure VIBRATION in -24vdc and why we adjust gap voltage -9vdc to 10-vdc? i am trying to get this information since 5 years, yet i haven't get reliable answer, i hope i can get from you.
What is the difference between security constraint unit commitment and security constraint optimal power flow?
how is the testing of an REF relay? what are the test REF circuit having?
Application Comparison between 22KV (UE)and 33KV (E) system. Are we allowed to use 33KV (E) cable in lieu of 22KV (UE) cable. What are the technical disadvantages.
take 100kva DTR( delta/wye ), what ll happen if we connect 11kv to LT side instead of connecting to HT side? will the DTR behave as a step up transformer or something else????
raleigh method
Difference between rating factor of cable and derating factor of cable?
In layman terms, what is the difference of Dielectric strength and dielectric constant when speaking of an insulating oil
What is meant by turbo alternators?
in my working site. momentary jerck in electrical supply ocurred frequently which cause of multiple losses in our electrical equipements. how can we protect our electrical machines and equipements in this situation.
What's mean HVF & HAF in Vacuum Circuit Breaker?
Pl. brief about break-down maintenance of machine tool.
What happens if the series current double?
Is neutral transformer can be called as control transformer?