Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

Why earthing transformer used in Distribution Sub-Station?

Answer Posted / engr. l. o. osuji

Hi questioner,
Earthing T/F or T/Fs are not required in distubution S/S.
For example, here in Nigeria the distribution volage for
the T/F is either 11/0.415kV or 33/0.415kV detla-star.
However, in Transmission S/S where there are 132/33kV star-
delta connected T/F or T/Fs earthing T/F or T/Fs are
necessary. The earthing T/F is connected on the 33kV side
of the main T/F while the star-point of earhing T/F is
connected to ground to provide an artificial star-point for
the main T/F. This so because 33kV distribution ground-
fault current must flow back to the main T/F. Earth fault
protection for the main T/F must sense this current and
isolate the main T/F otherwise the earthing T/F will roast
i.e. burn.

Is This Answer Correct ?    12 Yes 3 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what is the method of earthing of a transformer using electrodes?

2278


sir am giving jspl exam on 19th oct . i belong to eee, so plz send previous question papers ..........to dis id abhilash203@gmail.com

2573


direction of tarbine& genrator

2095


75 kw motor take 45 amp in no load delta in star 10 amp but in load it will take 160 amp but IR velue of winding above 500 at 1kw ph to earth and ph to ph. what problem it should be?

3728


help me with the question that might be ask on the interview for technical position

2293


if an insulated power and control cables of a running gas diesel gensets laid direct in an open trench i.e, trench bed is not rcc of a power house in which rain water, spillage water alwas exists and all power control cables remains submerged even when gas gensets of 480 kw each runningin on load. These power &control cables runs from power house to switchgear room through these trenches in which water remains most of the time. pl explain its merit & de-merit

1882


why we use Test Terminal Block in 11 KV and 33 KV electrical panels.

1379


What effect does a very low impedance have on the Voltage regulation? On the short-circuit current?

6305


what is the meaning of the symbol << >> put in transformer drawing

1990


explain different types of d.c motors?

1157


What size cable (based on voltage drop) is required to supply a 40 A three phase boiler if the wiring system is 75V single insulated cables installed in non-metallic rigid conduit 56m from the main switchboard? Voltage drop in the consumer's mains is 8V.

1982


Installation method of self treated earth electrode.

2056


What is meant by reverse polarity and how it can be fixed?

1270


What type of wiring series or parallel is used for conventional and addressable type FAS & why?

1803


reason of diode failure in alternator

1862