in our sub station why we step down firstly 33kv\11kv then
11kv to 430v. can we direct step down 33v to 430.v.
Answer Posted / devesh mishra
yes we can directly step down from 33/.433kv.
the lv side remains constant for 11 or 33kv & hv side
depends on load i.e,
for load upto 4 mva 11kv ht line is required,whereas
for load above 4 mva 33kv ht line is required.
Is This Answer Correct ? | 40 Yes | 25 No |
Post New Answer View All Answers
How to choose size of the cable w.r.to current carrying capacity ...
Starting Time of LT & HT Motor
In cable sizing calculation (determining the max route length of cable) why we choose the shortest length between cable length of full load current Iflc & starting current Istart?
tell me about roaster switch .& what is the function in transmission & distribution?
plese send me the oces/dgfs sylabus and previous year question pattern of electrical engg.?
how to calculate the torque of a motor?
Is it true online ups having bypass mode if it is true then why we called ups because it is interrupting power when goes in bypass mode
what is power factor ? how we can calculate the low power factor and amount of capacitor for improve that low factor ?
why the check zone and main zone are used for Busbar Protn. scheem?
Please, if 1kw is equal to 1.25kva; how then do I know how many kva in 7.5kw?
What is Load sharing of Transformer ?
Hello seniors m an engineering student in 3rd yr..i want to know what are the software course in electrical field?i wanted to do certification course but i dont know much about the course?..Regards
How can a equal potential zone be carried out in conductors?
If we have to find the inductance of a dc shunt motor then by giving dc supply or ac supply and what is the reason for it. (this example is from "to determine the transfer function of a dc shunt motor ")
What is the exact formula for one weber of magnetic flux?