Method of findingthe dry ingredient quantity of 1 m3
concrete.
Answer Posted / naresh thakur
soppose, concrete mix ratio = 1:1.5:3
then, sum = 1+1.5+3 = 5.5
as we know,dry material required for 1 cum. of concrete =
1.54 cum.
then we can find -:
(1) cement = 1*1.54/5.5 = .28 cum. or .28cum.* 28.8= 8.06
bags.
(2) sand = 1.5* 1.54/5.5 = .42 cum.
or .42cum.* 35.3 = 14.83 cubic feet.
(3) coase aggregate = 3* 1.54/5.5 = .84 cum.
or .84 cum.* 35.3 = 29.65 cubic feet.
so, dry ingredient quantity required for 1 m3 of concrete-:
cement = 8.06 bags.
sand = 14.83 cft.
coarse aggregate = 29.65 cft.
do not forget to add 5 to 8 % addition matreial.
| Is This Answer Correct ? | 347 Yes | 36 No |
Post New Answer View All Answers
Why are steel plates inserted inside bearings in elastomeric bearing?
How to calculate dry of volume of concrete constant?How it comes 1.54 or 1.57
Bearing capacity of soil determined as per ASTM is to design the foundation size.what is the importance of EV1/EV2 value as per DIN .My consultant ask me to test the the soil as per din to find out this ratio to assess the compacted strength of soil ,,?? is it meaning full ??
Which is the direction for positive angle?
How to calculate steel for beam slab and column
Define What is the meaning of a blue land surveyors flag?
how to absorb to site basic corrections? which are the important correction?
WHAT IS THE CAUSES OF RUTTING ON FLEXIBLE PAVEMENT?
can we find any technical issue if we are gong to change the dimensions of steel beams from one type to another type IE if there are any equievelant data base to find solution for problem of changeing sectios of beam from one type to another with the same cross sectional area.
The largest size of paper used in plotter to print the drawing made by Autocad .
how much cost of single coat 20mm thick plastering per sqre meter
Which are the top apps for you civil engineering?
why the openings of sieves are square io size?
please what are the required bars for a beams of 6mx6m and 450x300mm, one is continuous and the the second is discontinuous ..Its a commercial building (church)
what is the type of earthing