Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How to find out the quantity of steel FE415

Answer Posted / santosh singh

QUANTITY OF STEEL :3.14 / 4 * d2 * 7850
(sq. of d)
EG. IF DIA OF STEEL ROD IS 12mm = 12/1000 = 0.012metre
QUANTITY OF STEEL PER METRE RUNNING STEEL ROD IS
= 3.1416/4 X [0.012]2 X 7850 = 0.89 KG/METER
OR IT CAN BE FOUND BY ....
QTY OF STEEL = d2/162.19 kg per running meter
where d is dia of bar

good luck..........

Is This Answer Correct ?    75 Yes 8 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

 What is difference between limit state and working stress method? How it is applies in building structure.

2272


How to find coloumn vertical cut length floor to floor & lap + bend or anything plz clearfiy

1976


pls give me ans to ACT formula cube testing porpuse

3008


Difference between pre-tensioning and post-tensioning.

1112


How many Rod required for 58 feet by 24 feet roof slab which is supported by 5 * 3 = 15 Column. Six Stored building Roof Slab = ? Ton 15 Column = ? Ton Slab Beam = ? Ton

2084


What is pre-stressed concrete?

1062


How do you convert wind speed into force?

1251


How to Rectify deep crack formed on Brick Wall? Explain the method of rectify the defect?

7767


Explain the difference between shear and tensile strength.

1047


what is meant by shear center?????

2577


Can we weld hot rolled steel ASTM A615 ? Please Give the detail answer please thanks alot

2205


sir when can we expect the AEE results and when will be the interviews sheduled please guide us in this regard thanking you

2397


Caching, Multithreading and RAMBUS are 3 methods for resolving the Bottleneck problem. Please give an explanation for each one (how are they resolve the problem?)

2210


How high should the water tank be to provide a 60 psi at base of this water tower?

1078


States some of the commonly used commands in cad software’s?

1167