What are the technical reasons for soaking transformers for
various times before allowing them to pick load after a
fault ?
Answer Posted / al kafaah
I think the transformers are soaked with normal operating
voltage level as testing with HV of the transformer
insulation, winding at site is impractical as well not
economical. Besides soaking allows the transformer
insulation to be tested for operating voltage such as oil
(so that oil inside is not breaking down) or winding
insulations, short circuits, inter-turn faults (though
these items are individually tested for its correctness at
site test, but not as a whole unit at Normal operating
voltage). Whereas the Switchgears and Cables which are
other Primary circuit components are tested with High
voltage even at site
| Is This Answer Correct ? | 25 Yes | 8 No |
Post New Answer View All Answers
What is the difference between resistance grounding system and resistance earthing system?
trasnfarmaer core make
Is it required to use Automatic transfer Switch in L&T panel board if we use AMF panel with DG set? How the single line diagram will be? Please forward the material to sreenu_207@yahoo.co.in
What is the difference between vector surge relay (78) and Pole slip relay (98G)
How to test REF relay testing for LV panel as per Kahramaa standard?
What is meant by time harmonics and space harmonics?
from which formula we select a capacitor rating?
hello everybody. what does an abnormal stator winding impedance or dc resistance show? thanx
how to carried out DAR test in 11 KV Alternator ?
What is meant by bus bar protection?
How to work definite,over pluxing,revers power,OSR relay
What is the necessary and sufficient condition for stability.
The sodium vapor lamp is not glows when it is connected a distance of 5 meters above from gearbox, why ?
what is the need to express current and voltage in rms value? rms value is also called as effective value,what is effective value?
What is the role of feedback in a closed loop control system?