Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

For testing 33kv cable hipot testing. How much kv we have to
Apply .Give in details.

Answer Posted / bapi

AS HI POT TEST IS CONDUCTED IN DC SO APPROX. 1.5 TIMES OF
AC SUPPLY VOLTAGE IS APPLIED FOR 1 MINUTE.
FOR 33 kV CABLE APPROX. 50kV FOR 1 MINUTE WILL BE APPLIED.
FOR TESTING OF "R" PHASE WE HAVE TO SHORT "Y" AND "B" PHASE
ALONG WITH ARMOUR & IT SHOULD BE EARTHED. SIMILARLY FOR Y &
B PHASE.
AFTER EACH PHASE TESTING IT SHOULD BE DISCHARGED THROUGH
DISCHARGE RODS.

Is This Answer Correct ?    66 Yes 30 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what is the differencce inn series and cascade connection??

4719


What are the main parts of central chiller plant? Explain the function of each stage.

4797


How i can decide that HVDC line is best for transmission.

1901


WHAT SHOULD BE THE BEST CURRENT RATINGS (PRIMARY / SECONDARY)FOR A CT INSTALLED AT THE INCOMING 11KV PANE? WILL IT BE CALCULATED ON THE BASES OF MAXIMUM DEMANT VALUE OR ON SUM OF ALL TRANSFORMER'S KVA? NOMALLY MAX DEMAND REPRESENT THE MAXIMUM OPERATING LOAD OF THE PLANT AND TOTAL KVA OF (SAY 5 NUMBERS TRANSFORMERS) REPRESENT THE CONNECTED LOAD. WHICH i.e. MAX DEMAND KVA OR CONNECTED KVA ARE BETTER TO USE FOR CT CURRENT CALCULATION? PLEASE ANSWER.

1906


1)we have 1000 cfm Blower,Dia-1Mtr,Velocity of air 94 m/s 2)We have Natural Air velocity 94m/s 3If i Put Wind Mill in natural air ,speed is 94m/s Then it will generate Assume 100kw 4)If i put same wind mill across the Blower,air speed is same 94m/s now the Question is Will it generate 100 kw?

1992


WHAT WOULD BE THE FORMULA OF WIRE GAUGE FOR A FULL LOAD CURRENT

2303


Tell me all plants load factors i.e which plant operating on which load?

2090


what is the formula for computing cable tray size & capacity

2162


How PADO software increase the efficiency of power plant?

6475


If the feeder rating is 7.5 kw or 10 HP star-delta feeder, MCCB is taken as 63 a, contactors-32 a, how much will be the OLR rating or which range OLR should be considered when we concern about type-2 coordination?

2311


What are the section criteria for cables. Now everywhere XLPE power cable is used or PVC is also used?.

1662


Explain the operation of variable frequency transformer?

1132


pls tell me about ups internal connection & we have given only 3 phase supply to ups system how get 4 wire (R Y B N )

2756


a 230v transformer with step down ratio 19:1.it has 2000turns on primary and rated 25va calculate max primary current no of secondary turns volts/turn

1538


How do I calculate/select Droop CT ratio for various capacity of generators?

3646