What is your management Style

Answer Posted / tushar waghode

Depends upon the criticality of the stage the project is,
organization and client culture, the maturity, seniority,
and dependability of the resources working on the project
and the state of the project, like if the project is in
trouble shooting mode or things are going as planned.
It can vary from centralized to consensus. I generally
prefer a consensus management style but with a veto power
(final say) to ensure organization and project interests do
not clash with resource interests.

Is This Answer Correct ?    46 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

You are the project manager for Changing Tides video games. You have produced a project network diagram and have updated the activity list. Which process have you just finished? A. The Activity Sequencing process, which identifies all the specific activities of the project B. The Activity Sequencing process, which identifies all the activity dependencies C. The Activity Duration Estimating process, which diagrams project network time estimates D. The Activity Duration Estimating process, which identifies all the dependent activities of the project

524


Which of the following is true regarding schedule variances? A. They impact scope, which impacts the schedule B. They sometimes impact the schedule C. They always impact the schedule D. They never impact the schedule

608


Which of the following is true? A. Discounted cash flow analysis is the least precise of the cash flow techniques as it does not consider the time value of money. B. NPV is the least precise of the cash flow analysis techniques as it assumes reinvestment at the discount rate. C. Payback period is the least precise of the cash flow analysis techniques as it does not consider the time value of money. D. IRR is the least precise of the cash flow analysis techniques because it assumes reinvestment at the cost of capital.

497


What change would you like to bring in the management of your previous organization ?

547


Deliverables can be described as: A. The purpose for undertaking the project B. The verifiable results of products or services that must be produced to consider the project complete C. The specifications regarding the goals of the project that must be produced to consider the project complete D. The measurable outcomes of the project goals

636






The tools and techniques of Source Selection include all of the following except: A. Contract negotiation B. Work authorization system C. Weighting systems D. Independent estimates

678


The Project Integration Management knowledge area is made up of which of the following processes? A. Initiation, Project Plan Development, and Integrated Change Control B. Project Plan Development, Project Plan Execution, and Integrated. C. Project Plan Development, Initiation, and Scope Planning D. Initiation, Scope Planning, and Integrated Change Control

539


Which of the following processes assess the likelihood of risk occurrences and their consequences using numeric probability assignments? A. Qualitative Risk Analysis B. Risk Identification C. Quantitative Risk Analysis D. Risk Response Planning

728


Which of the following are the outputs of the Contract Closeout process? A. Project archives, formal acceptance and closure, contract file B. Contract file, formal acceptance and closure C. Project archives, contract file D. Contract file, formal acceptance and closure, lessons learned

511


Which of the following processes serve as inputs to each other? A. Executing and Controlling B. Planning and Executing C. Planning and Controlling D. Executing and Initiation

620


Which of the following processes negotiates the sequence of award by rank ordering the proposals? A. Source Selection B. Solicitation C. Contract Administration D. Procurement

687


You are working on a project that will upgrade the phone system in your customer service center. You have used bottom-up estimating techniques to assign costs to the project activities and have determined the cost baseline. Which of the following is true? A. You have completed the Cost Estimating process and now need to complete the Cost Budgeting process to determine the project's baseline. B. You have completed the Project Plan Development process and established a project baseline to measure future project performance against. C. You have completed the Cost Estimating process and now need to complete the Project Plan Development process to establish a project baseline to measure future project performance against. D. You have completed the Cost Budgeting process, and the cost baseline will be used to measure future project performance.

623


You are the project manager for a nonprofit organization. Your project has come about due to a social need. Your sponsor wants to get right to the Planning process. However, you know that a scope statement should be published prior to proceeding to the Planning processes. All of the following are true regarding scope statements except: A. It documents roles and responsibilities. B. It can be modified to reflect changes to the scope of the project. C. It describes the project deliverables, requirements, and objectives D. It serves as a baseline for future project decisions.

571


Obtaining formal project plan approval and sign-off is important for all of the following reasons except: A. Stakeholders are able to recommend a project Planning methodology to follow throughout the remaining process groups. B. Stakeholders are aware of the project details, which make them more likely to participate in future project decisions. C. Stakeholders will be more likely to cooperate. D. Stakeholders are aware of the specific details regarding project schedules, budgets, and risks.

911


Describe capability maturity model (cmm).

534