why synchronization done in clockwise direction?
Answer Posted / shonali
there is no CW and CCW synchronization it depends on the
speed difference
synchronization is connecting our generator to grid by
matching with the grid frequency.
a synchroscope is used if our generator speed is less than
grid speed (frequency) the synchroscope rotates counter
clock wise (lag).
if our speed is high the scope needle rotates CW (lead)
if it is equal the needle stops
| Is This Answer Correct ? | 21 Yes | 6 No |
Post New Answer View All Answers
what parameters should we check to reduce the power bill
what is data block in plc ? How the values of data block are written and read by hmi ? what is the difference between function and function block ?
What is the range of the stator resistance of 3 phase induction motor?
Why do we mostly prefer to generate and distribute electricity in 3 phase and not in 4 phase or 5 phase?
Why 30kw 40 hp 4 pole 3ph induction motor over heated?any steps on reduction in heat?
when generator short circuit condition, the current how dissipates. or at short circuit voltage not available then current how can flow?
how we control automatic generator i'e with to supply (main supply and local generator) when the main supply was break to supply the local supply automatically to begin supplying power.I now this control circuit is the combination of contactor time delay contactor switch and overload relay .but my question is how we combine those component thank you
which pump used in WTP explain the function of VFD how to dtermine capacitorbank of capacity one plant
List examples of current sources?
why don't we use the generator as a motor? and what will happen?
Type of motor stater detail and working detail
Why the efficiency of a three-phase induction is the motor is less than that of a three-phase transformer?
A power transformer 4MVA/11KV/0.415Kv has been out of use in 12years. what maintenance actions/test need to be carried out before energizing.
why ct's&pt'S out put called as burden,why compelsary short ckt the secondary of ct's while removing the burden?
Please explain the following and how these are working with PLC unit 1.I/O Module 2.I/O Device 3.Adaptor Card 4.Ribbon Adaptor 5.RS 485-FC