If the capacitor bank is installed in switchyard say
132/22kv then on LT side say 22kv/0.433kv is it necessary to
install capacitor bank for maintaining power factor. if pf
is maintained on HT side then will that be maintained on LT
side as well.if not then how&why??????/ please
explain...........
Answer Posted / zahid noor
If capacitor bank is installed in switchyard & capacitors
are connected on HT side , it will try to balance losses of
transmission line and not towards LT side, where as for
maintaining /increasing LT side voltage, we need to install
seperate capacitors nearer to load so as to maintain PF at
LT side also depending upon connected load & distance of
equipment connected in LT side.
| Is This Answer Correct ? | 12 Yes | 0 No |
Post New Answer View All Answers
define digital electronic
I HAVE BEEN SELECTED FOR APGENCO A.E(ELECTRICAL) 2008.HOW MUCH WEIGHTAGE FOR INTERVIEW AND WRITTEN TEST.HOW I HAVE TO PREPARE. PLEASE GIVE INFORMATION IF U KNOW.WHAT ABT G.D THIS TIME.CALL RATIO 1:2
How does HT work & Voltage required?
75 kw motor take 45 amp in no load delta in star 10 amp but in load it will take 160 amp but IR velue of winding above 500 at 1kw ph to earth and ph to ph. what problem it should be?
We have a distribution transformer of 750KVA/11kv/440v and an AVR (Servo Stabilizer) of 750KVA on the LT side of distribution transformer. Also we have an ACB of 1200A on the output of distribution transformer (that is on the input of AVR). We want to have an MCCB on the output of AVR. What should be the rating?
what is the AC Plant and how can do the work with parts and picture tell us 150 Tr
pls tell me about ups internal connection & we have given only 3 phase supply to ups system how get 4 wire (R Y B N )
why 5kW motor becomes unbalance if its relay trip 1st time and its set value is 7.0 A
What are the symptoms of a bad PG card of a drive (inverter) esp. of Yaskawa Ac Drives (inverters) G7 ?
Is there any question in the name of Static Switch in UPS??
how to determine ct ratio in ht vcb?
i ha done my 10th with 71% ,ITI with 81% 11th with 75% 12th 43% apprentiship with 71% in SAT i secure 1390 ,TOEFL 27 i was refused four times and in all me interview visa officar told that i am not Qualify for study in USA but i completed my 12th yes i got low persentage in my 12th but i seen to much student they already got visa with them 3 or 4 backlocs so why they are refused me ?
11KV AND 22KV NETWORK KW CAPACITY IN RING AND RADIAL?
What is MS-EXCELL?
why do we use 25kv supply for traction purpose?