If the capacitor bank is installed in switchyard say
132/22kv then on LT side say 22kv/0.433kv is it necessary to
install capacitor bank for maintaining power factor. if pf
is maintained on HT side then will that be maintained on LT
side as well.if not then how&why??????/ please
explain...........
Answer Posted / kola raju
If the capacitors are installed in the ht side the pf of
the line improves but not the plant.And the plant pf is in
poor condition only which may leads to the losses on our
side and reactive load on the transformer may increase so
even if we have capacitors on ht side it is advaisable to
kept the capacitors on load side also.
| Is This Answer Correct ? | 9 Yes | 3 No |
Post New Answer View All Answers
how to calculate the loss tangent of electrical cables
Match the following a)(X'+Y') b)X'Y' C)XY 1)NAND 2)NOR 3)Carry
we have a lot of model of rectifier but thyristor rectifier is the most rectifier that use in power system. Do you know why this rectifier is used?
Use of switch mode power converter in real-time basis?
how to determine Sq.mm size of finolex power cables.
please send the last 5 years {{{JUNIOR ENGINEER - ELECTICAL, ELECTRONICS RRB CHENNAI and secundrabad}}} TECHNICAL question papers TO MY EMAIL ID dinesh100701@gmail.com
What is the one main difference between ups & inverter ? And electrical engineering & electronics engineering ?
can anyone give an idea about dia calculation in cold rolling mill
To prove the capacity of a 10MVA transforemr with 6.5% impedance by a short circuit test how much power is needed to inject an impedance voltage if we have to arrive for its rated current?
please I wont know how to calculate the vector group for power transformer ZNyn11 best regard.
I need the list of Universities who have summer intake for BS degree in Electrical Engineering.?
What is the drawback of class b amplifier? How is this minimized?
How to select the gauge of wire for winding of motors? How to select number of turns for winding of three phase induction motor?
How does a tertiary winding filter harmonic(espcially 3rd one) from entering into load system?
what is level 2 automation?