WHAT AC (HI VOLTAGE TEST) VOLTAGE SHOULD APPLY FOR 33KV
CABLES.EXPLAIN IN DETAIL
Answer Posted / ran7it
u can use a hipot kit. for a 33kv cable the voltage 2 b
applied can b determined by formula (2E + 1),,whr E is the
system voltage,so for tis case it comes as 2*33 +1=67kv.
tis 67kv is mostly applied for the first time in factory
testing..after tat only 60-70% of 67kv sud b applied.
the cable has to withstand tis voltage for 1min..
| Is This Answer Correct ? | 27 Yes | 4 No |
Post New Answer View All Answers
Can anyone tell me some hints about what type of questions are asked by the interviewer by an Electronics engineer when company is installing an IPP and wants a team of engineers?
How to decide whether A / B / C / D curve type MCB should be used?
explain different types of d.c motors?
how technical is calculated in 11kv line and lt line
What is the actual meaning of thermal power efficiency ?
Why are lt windings placed near the core?
What is safety of Ht panel
What facility we get after CT secondary earthing and how?
what is the purpose of silicon dropper used in battery charger?
what is meant by re-rolling motor? how it differs from standard motor?
54 Comments Alok and Bhanu play the following min-max game. Given the expression N = 38 + X*(Y – Z) where X, Y and Z are variables representing single digits (0 to 9), Alok would like to maximize N while Bhanu would like to minimize it. Towards this end, Alok chooses a single digit number and Bhanu substitutes this for a variable of her choice (X, Y or Z). Alok then chooses the next value and Bhanu, the variable to substitute the value. Finally Alok proposes the value for the remaining variable. Assuming both play to their optimal strategies, the value of N at the end of the game would be?
why the starting voltage drop in a cable needs to be limited?what is percentage of the voltage drop allowed during starting?
Hi,iam a diploma in electrical engineering.rtd from indian air force in apr 2007.prsently working in reliance next link as a network maintenance engineer since 2007,can i get a job in motherson sumi.
Can we transmit digital signal to long distance ?
Why you want to join non technical field when you are an engineer?