In SAP Open and Close period is maintain in FI & MM module
separately.
FI T.Code OB52.
MM T.Code MMPV
in FI we can open and close the period individually
for eg. only GL posting or asset posting.
like we can close GL, Asset,AP, AR. In FI whenever need we
can open it and post any entry, but definitly it will
affect the balance sheet and p&l, so we should not open it
without higher person's perior consent.
but in MM we can not maintain more than 2 two periods.
If you closed the period in MM we can't reopen it. so
carefully handle it. FI no problem.
If any mistake plz correct it. bkaz period closed is vital
areas.
Is This Answer Correct ? | 13 Yes | 2 No |
Post New Answer View All Answers
GL posting as per order type :- Hi, We have a requirement "For free of charge order zfd , all these orders should hit one GL irrespective of movement type (it may 901 or 601)"
what is documentation in SAP FI? and what is reporting in SAP FI?
Is it possible to use standard sap co-product functionality in repetitive manufacturing?
What is a plan version? : co- cost center accounting
What items are required in a financial statement version? : fi- general ledger master data
What do you mean by the depreciation?
What are the categories of variances in co-om-cca? : co- cost center accounting
What is group asset in sap? When you will use this? : fi- asset accounting
Name some settlement receivers for co internal orders?
Explain the input variance? : co- cost center accounting
Hi, I am a FI consultant with 1.6 yrs experience..can anybody help me to learn CIN FI part..mail me if u have any documents related to that..rajendranmba@gmail.com....thanks.
Where to assign activity type in cost centers? Or how to link cost centers & activity types?
What are the interaction with abaper in project especially for screens, conditions and cutover plan?
What is the configuration setting to be done for posting the accrual in the actual costing run?
How do you maintain the number range in production environment? Do you directly create it in the production box or do you do it by means of transport?