Method of findingthe dry ingredient quantity of 1 m3
concrete.
Answer Posted / b.subhash
Estimating Quantities of material needed.
1. Calculate the volume of concrete needed.
2. Estimate the total volume of dry material by
multiplying the required volume of concrete by 1.65 to get
the total volume of dry loose material needed (this includes
10% extra to compensate for losses).
3. Add the numbers in the volumetric proportion that you
will use to get a relative total. This will allow you later
to compute fractions of the total needed for each
ingredient. (i.e. 1:2:4 = 7).
4. Determine the required volume of cement, sand and
gravel by multiplying the total volume of dry material (Step
2) by each components fraction of the total mix volume (Step
3) i.e. the total amount cement needed = volume of dry
materials * 1/7.
5. Calculate the number of bags of concrete by dividing
the required volume of cement by the unit volume per bag of
cement (0.0332 m3 per 50 kg bag of cement or 1 ft3 per 94 lb
bag).
For example, for a 2 m x 2 m x 10 cm thick pump pad:
1. Required volume of concrete = 0.40 m3
2. Estimated volume of dry material = 0.4 x 1.65 = 0.66 m3
3. Mix totals = 1+2+4 = 7 (1:2:4 cement:sand:gravel)
4. Ingredient Volumes: 0.66 x 1/7 = .094 m3 cement
0.66 x 2/7 = .188 m3 sand
0.66 x 4/7 = .378 m3 gravel
5. # Bags of cement: 0.094 m3 cement / .0332 m3 per 50 Kg bag
= 2.83 bags of cement (use three bags)
| Is This Answer Correct ? | 158 Yes | 44 No |
Post New Answer View All Answers
What is the substitute of Mastic Asphalt?
cud any one send me tech quest paper(civil engg) at tarizus@yahoo.com
i have a interlock pavement work.i need to compact about 2000 sq metres of sub base grade c of thickness 15 cm.what is the amount of water required for compaction ??
How do you measure water flowing through 300mm diameter pipes?
how to calculate spacing rod in column
The building has 12 columns of 12x9 in 3 rows of 4 each in a plot of 50'x30', The central row is strengthened with 16mm twisted rods. The roof area is 1500 sft including balconies. calculate the load factor per sft. Also indicate the number of roofs the building can withstand.
what is the use of water bar in water tank and is this an extra item in estimate?
for 32 dia (EQR HYSD steel) bar how much deduction for 45 and 90 degree band
What is the zero value in quantity surveying
how to calculate the mortar for 10'*10' size room for both plastering and for masonry work?
1) What is meant by C-soil in geotechnical Engineering? 2) What is Eve board? 3) What will happen when heat is applied to cement? 4) what do you understand by the lateral dimention ?
Civil engineering related
How many kilo-newtons equals 1000 kilogram?
What happens when water mixed with cowdung is used for priming instead of water for lifting water in pumps?
how to calclate the SHUTTERING TAKEN CONCRETE LOAD? WHAT IS THE LOAD BEARING CAPACITY IN STEEL SHUTTERING PLATE? WHAT IS THE CONCRETE LOAD IN (MASS) IN THE SHUTTERING PLATE. PLATE SIZE IS 120CM* 90CM CONCRETE WALL LENGTH IS 10M ,WIDE IS 60CM, HEIGHT IS 1.2M PLS TO SENT THE CALCULATION.