hi, 1)totally how many jobs created in ur project
2)what is ur datamart size & Dwh size
3)How secure ur project
4)could u plz tell be about testing process after complete
the job will run sucessfully or not in Datastage
Answer / kiran
1)totally how many jobs created in ur project?
Ans:Depend upon duration: suppose u mentioned as like 12-15
months:52 jobs
2)what is ur datamart size & Dwh size
Ans: no one know about size of the DWH but u can define as
like it should be tera bites and datamart size is 6 gb
3)How secure ur project
Ans:take care under Admin
4)could u plz tell be about testing process after complete
the job will run sucessfully or not in Datastage
| Is This Answer Correct ? | 12 Yes | 0 No |
Describe the architecture of datastage?
I have load a Dataset in UAT with 2 Node configuration, imported the job into PROD environment which is 4 node configuration and using this DataSet as SRC to other job. will the job run fine or give any errors? If job runs fine, on how many nodes? 2 nodes or 4 nodes?
Scenario : I have 2 jobs say job A and Job B with parameters x and y respectively. I need to create a sequence job. If we pass parameter x then Job A should run, If we pass parameter y then Job B should run, if we dont pass any parameter then Both Job A & B should run.
what is initial load and incremental load
how can we perform the 2nd time extraction of client database without accepting the data which is already loaded in first time extraction
What is developer responsibilities in UAT (user acceptance testing and Post implementation phase?
what is the diff b/w switch and filter stage in datastage
How the ipc stage work?
I have oracle enterpaise stage, oracle bulkloader stage, ODBC stage and I want to load data in to target, which of the above stages do I need to use and why?
What are the partition techniques available in your last project?
I have a scenario like Deptno=10---->First record and last record Deptno=20---->First record and last record Deptno=30---->First record and last record I want those first and last records from each department in a single target. How to do this in DataStage, any one can assist me. Thanks in advance.
What is apt_config in datastage?