How do you ensure that your project is always on track?
No Answer is Posted For this Question
Be the First to Post Answer
You are a project manager for Candy Works candy factory. Your project involves reporting information from the newly installed candy-counting machine to the financial system. This will give executives the ability to see production run counts at any rime during the day. The project sponsor has promised you a bonus if you get this project completed two weeks sooner than the scheduled project end date. The bonus will come in handy on your trip to the Bahamas planned for later this spring. You've got a few remaining project activities to wrap up before you can close out the project. Which of the following is the most appropriate response? A. You tell the sponsor the project is complete and treat the remaining activities as though they're problems that came up after project closure so that you can still get the bonus. B. You tell the sponsor the remaining activities are outside the scope of the project so the project really is completed and collect your bonus. C. You tell the sponsor the stakeholders added these requirements after the project was well under way and you never agreed to include them in the project so the project really is complete, and you collect your bonus. D. You tell the sponsor you aren't going to make the two-week early completion date as there are remaining activities to finish up.
Explain the Principals of Management
0 Answers Mahatma Gandhi University,
You are the project manger for Xylophone Phonics. They produce children's software programs that teach basic reading and math skills. You are ready to assign project roles, responsibilities, and reporting relationships. Which project Planning process are you working on? A. Resource Planning B. Organizational Planning C. Staff Acquisition D. Human Resource Acquisition
What are the inputs to the Initiation process? A. Product description, strategic plan, project selection criteria, and historical information B. Product description, strategic plan, project overview document, and historical information C. Strategic plan, project overview document, feasibility study, and historical information D. Product description, strategic plan, constraints, and assumptions
What is the difference between contingency and mitigation plan?
Which of the following tools and techniques shows the impacts of one decision over another as well as the probability and cost of each risk along a logical path? A. Simulation B. Decision tree C. Probability/impact risk matrix D. Sensitivity analysis
You are the project manager for Heartthrobs by the Numbers Dating Services. You’re working on an updated Internet site that will display pictures as well as short bios of prospective heartbreakers. You have your activity list and resource requirements in hand and are planning on using qualitatively based durations and reserve time to determine activity durations. Which of the following is true? A. You are using inputs of the Activity Duration Estimating process. B. You are using tools and techniques of the Cost Estimating process. C. You are using tools and techniques of the Activity Duration Estimating process. D. You are using inputs of the Cost Estimating process.
What are the framework activities and umbrella activities?
All of the following are true regarding the tools and techniques of Activity Sequencing except: A. GERT uses analogous methods. B. GERT allows for loops. C. GERT is a conditional diagramming method. D. GERT allows for conditional branches.
The project schedule is used to determine all of the following except: A. Cost estimates B. Activity start dates C. Float times D. Activity end dates
The purpose of the Initiation process is to: A. Formally recognize the existence of a project or project phase B. Formally recognize the need that brought about the project be it marketing demand, customer requests, business need, technological advances, or legal requirements C. Formally recognize the stakeholders of the project and identify them in the project charter D. Formally recognize the project sponsor and document his or her project goals
Which of the following is displayed as an S-curve? A. Gantt B. Cost baseline C. Critical path D. PERT