If it took eight men ten hours to build a wall, how long would
it take four men to build it?
Answers were Sorted based on User's Feedback
Answer / maddy
total manhours is 8 x 10 =80...
four men would take 80/4=20 hours
| Is This Answer Correct ? | 2 Yes | 2 No |
which of the following is said to be an important aspect of industrial relation? 1.profit and loss of the org 2.future expansion programme 3.conflict and co operation 4.quality control 2. The Govt strategy in maintaining indusstrial relation in india is 1. laissez faire 2. total intervention 3. required intervention 4. none of above
Indian rubber obtained from the latex of which plant?
what is mean CTC
please send the model papers for the exam of idbi for the post of assistant manager
Anyone can U plz send me railway recruitment track superior previous questions
what abt RBI Hikes
1 Answers State Bank Of India SBI,
send me different english vocabulary which is used in general spoken language and words and their meanings
what is the name of tax in vaidik cal?
Can u tell me about the work function of a probationary officer?
Any one is there who got selection in written exam of SBi held on 1 march 2009 for himachal paradesh general category. i hv got selection for their. plz help me about interview question.
0 Answers State Bank Of India SBI,
what is the exam pattern of rrb assistant loco pilot exam?
Feathery stigmas seen in which family?
ICET (321)