Thirty men take 20 days to complete a job working 9 hours a
day.How many hour a day should 40 men work to complete the
job? (a) 8 hrs (b) 7 1/2 hrs (c) 7 hrs (d) 9 hrs
Answers were Sorted based on User's Feedback
Answer / seema
FOR 30 MEN D NO OF WORKING DAYS=20
FOR 40 MEN D NO OF WORKING DAY=20
MEN =30 40
DAYS =20 20
HRS PER DAY =9 x
30*20*9=40*20*x
so x=6.75hrs
| Is This Answer Correct ? | 32 Yes | 16 No |
Answer / satish pandey (gbpuat pantnaga
40/30=9/x
x=6.75
correct answer=7
| Is This Answer Correct ? | 13 Yes | 8 No |
Answer / shylu
9 hrs s d correct answer....
for 30 men d no of workin days=20
for 40 men d no of workin days=15
men : 30 40
days : 20 15
hrs per day : 9 x
30*20*9=40*15*x
so x=9hrs
| Is This Answer Correct ? | 20 Yes | 25 No |
Find the correct meaning of the following phrase: Man of few words
At 6'o a clock ticks 6 times. The time between first and last ticks is 30 seconds. How long does it tick at 12'o clock.
with 4/5 full tank vehicle travels 12 miles, with 1/3 full tank how much distance travels
A work is done by the people in 24 min. one of them can do this work a lonely in 40 min. how much time required to do the same work for the second person.
There are 19 horses in a stable. All but eight died. How many will be left in the stable?
A man walks east and turns right and then from there to his left and then 45degrees to his right.In which direction did he go ?
0 Answers Canara Bank, EDS, Google,
9/10 or 10/11 which is greater.
Do you have SBI's Bank Examinations Preliminery Solved Question papers Of Previous years? If You Have Please send me to my I.D. given Below.
X < 0, Y <> 0 then what is the possibility that the result is always positive?
4. When 2 dice are simultaneously thrown, is it possible that one of the ____ occurs. Result 1: A 5 and a 6 are obtained. Result 2: A 5 is obtained twice. Select the response that you agree with the most.
If on an item a company gives 25% discount, they earn 25% profit. If they now give 10% discount, then wat % profit they make?
The population of a city increases @ 4% p.a. That is an additional annual increase of 4% of the population due to this influx of job seekers, the % increase in population after 2 years is