Trapezoidal footing length = 2m , B=1.7m D=0.5m and d-
0.15m. Can anybody help and calculate quantity of concrete
by explaining all formulas involved.

Answers were Sorted based on User's Feedback



Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quanti..

Answer / ashok kumar chaudhary

Dear Sir,

SOLUTION :-

=((LxBxd)+(LxBxD/2))M3
Here L=2.0M
B=1.7M
d=0.15M
D=0.50M
((2.0x1.7x0.15)+(2.0x1.7x(0.50-0.15)/2))
=((0.51)+(3.4x(0.35/2))
=((0.51)+(0.595))
=1.105 M3 Ans.

Is This Answer Correct ?    0 Yes 0 No

Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quanti..

Answer / anand shinde

h=(D-d)

(D-d)/3x(a1+a2x(under root a1xa2)

Is This Answer Correct ?    0 Yes 1 No

Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quanti..

Answer / banambar pradhan

Dear all,

DURING THE PERIOD OF CONSTRUCTION TRAPIZODIAL COMES OVER THE
RECTANGULAR.
FORMULA IS-SQUARE+TRAPEZOIDAL

SQUARE =2X1.7=3.4XDEPTH 0.15=0.51 M3

TRAPEZOIDAL=H/6(A1+A2+4((A1+A2/2)^2))

SO=0.5/6(2^2+A2VALUE NOT GIVEN IN THIS QUESTION+4(2^2+A2
VALUE NOT GIVEN/2)^2))
IF A2 VALUE COULD HAVE GIVEN THEN WE CAN GET THE ANSWER EASILY

Is This Answer Correct ?    0 Yes 1 No

Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quanti..

Answer / naresh

u can calculate easily
suppose in trapezoidal footing we always find d &D
D - l * b * h
d- bottom l & b
top l& b after than calculate center of top & bottom
lets define l = 2m b =2m bottom
l = 1m b = 1m top then centre of both 1.5 × 1.5 multiply by half d .

Is This Answer Correct ?    0 Yes 1 No

Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quanti..

Answer / karthikeyan

Volume = ((D+d)/2)*B*L
= ((0.5+0.15)/2)*1.7*2
= 0.325*1.7*2
= 1.105 cubic meter

Is This Answer Correct ?    45 Yes 68 No

Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quanti..

Answer / mohd.younus ali , je (pr )

Top Length = L1
Bottom Length = L2
Top Breadth = B1
Bottom Breadth = B2
Depth = D

Then simple formula is
(L1+L2)/2=L
(B1+B2)/2=B
The Quantity of Concrete is = L * B * D

Is This Answer Correct ?    16 Yes 51 No

Post New Answer

More Civil Engineering Interview Questions

why we used shahabad stone (ladi) in box type water proofing.what is the main roll of shahabad stone?

2 Answers  


How to construct a water sump in a rocky soil?

0 Answers  


How much kg of sand,cement will be for 1 sqmt(Blockwork-size 400x200x200)1:4 ratio & same for plaster

2 Answers  


How to calculate the quantity of cement in Cement Mortar M10 Concrete using 40mm metal

1 Answers   bscpl,


what is plate load test and what is the procedure of it and what is accessories which in use

2 Answers  






what is the minimum grade of concrete used in rcc(reinforced cement concrete)

8 Answers   Lok Sewa Aayog, Prestige,


If 16 mm dia hysd bar of grade Fe500 is needed in a beam but it is not available in the construction site but the beam has to cast in an emergency. Which dia of bar is to be used for for that situation? (If greater than 16 dia bar is not available at site)

2 Answers   Shreeji Associates,


Mix proportions of m30,m35,m40

2 Answers   L&T,


What is the full form of BHEL? A) Bharat hydroelectricity Limited B) Bharat Heavy Electronics Limited C) Bharat Heavy Electricals Limited D) Bharat Heavy Enterprises Limited

1 Answers   HPSSSB,


how much quantity of work we can get by rod benders per day

3 Answers   IVRCL, NCC, OWDM,


what is P.C.C ?

13 Answers   RCC,


for 1cum how much bag of cement is used for M20 grade

17 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)