Trapezoidal footing length = 2m , B=1.7m D=0.5m and d-
0.15m. Can anybody help and calculate quantity of concrete
by explaining all formulas involved.
Answers were Sorted based on User's Feedback
Answer / ashok kumar chaudhary
Dear Sir,
SOLUTION :-
=((LxBxd)+(LxBxD/2))M3
Here L=2.0M
B=1.7M
d=0.15M
D=0.50M
((2.0x1.7x0.15)+(2.0x1.7x(0.50-0.15)/2))
=((0.51)+(3.4x(0.35/2))
=((0.51)+(0.595))
=1.105 M3 Ans.
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / banambar pradhan
Dear all,
DURING THE PERIOD OF CONSTRUCTION TRAPIZODIAL COMES OVER THE
RECTANGULAR.
FORMULA IS-SQUARE+TRAPEZOIDAL
SQUARE =2X1.7=3.4XDEPTH 0.15=0.51 M3
TRAPEZOIDAL=H/6(A1+A2+4((A1+A2/2)^2))
SO=0.5/6(2^2+A2VALUE NOT GIVEN IN THIS QUESTION+4(2^2+A2
VALUE NOT GIVEN/2)^2))
IF A2 VALUE COULD HAVE GIVEN THEN WE CAN GET THE ANSWER EASILY
Is This Answer Correct ? | 0 Yes | 1 No |
Answer / naresh
u can calculate easily
suppose in trapezoidal footing we always find d &D
D - l * b * h
d- bottom l & b
top l& b after than calculate center of top & bottom
lets define l = 2m b =2m bottom
l = 1m b = 1m top then centre of both 1.5 × 1.5 multiply by half d .
Is This Answer Correct ? | 0 Yes | 1 No |
Answer / karthikeyan
Volume = ((D+d)/2)*B*L
= ((0.5+0.15)/2)*1.7*2
= 0.325*1.7*2
= 1.105 cubic meter
Is This Answer Correct ? | 45 Yes | 68 No |
Answer / mohd.younus ali , je (pr )
Top Length = L1
Bottom Length = L2
Top Breadth = B1
Bottom Breadth = B2
Depth = D
Then simple formula is
(L1+L2)/2=L
(B1+B2)/2=B
The Quantity of Concrete is = L * B * D
Is This Answer Correct ? | 16 Yes | 51 No |
why we used shahabad stone (ladi) in box type water proofing.what is the main roll of shahabad stone?
How to construct a water sump in a rocky soil?
How much kg of sand,cement will be for 1 sqmt(Blockwork-size 400x200x200)1:4 ratio & same for plaster
How to calculate the quantity of cement in Cement Mortar M10 Concrete using 40mm metal
what is plate load test and what is the procedure of it and what is accessories which in use
what is the minimum grade of concrete used in rcc(reinforced cement concrete)
8 Answers Lok Sewa Aayog, Prestige,
If 16 mm dia hysd bar of grade Fe500 is needed in a beam but it is not available in the construction site but the beam has to cast in an emergency. Which dia of bar is to be used for for that situation? (If greater than 16 dia bar is not available at site)
Mix proportions of m30,m35,m40
What is the full form of BHEL? A) Bharat hydroelectricity Limited B) Bharat Heavy Electronics Limited C) Bharat Heavy Electricals Limited D) Bharat Heavy Enterprises Limited
how much quantity of work we can get by rod benders per day
what is P.C.C ?
for 1cum how much bag of cement is used for M20 grade