An IS auditor performing an application maintenance audit
would review the log of program changes for the:

A. authorization for program changes.

B. creation date of a current object module.

C. number of program changes actually made.

D. creation date of a current source program.

Answer Posted / guest

Answer: A

The manual log will most likely contain information on
authorized changes to a program. Deliberate, unauthorized
changes will not be documented by the responsible party. An
automated log, found usually in library management products,
and not a change log would most likely contain date
information for the source and executable modules.