Which of the following is a strength of the program
evaluation review technique (PERT) over other techniques? PERT:
A. considers different scenarios for planning and control
projects.
B. allows the user to input program and system parameters.
C. tests system maintenance processes accurately.
D. estimates costs of system projects.
Answer Posted / guest
Answer: A
PERT considers different scenarios for planning and
controlling projects. Three time estimates, optimistic,
pessimistic and most likely are used to create a level of
uncertainty in the estimation of the time for individual
activities.
Is This Answer Correct ? | 6 Yes | 0 No |