An offsite information processing facility having electrical
wiring, air conditioning and flooring, but no computer or
communications equipment is a:

A. cold site.

B. warm site.

C. dial-up site.

D. duplicate processing facility.

Answer Posted / guest

Answer: A

A cold site is ready to receive equipment but does not offer
any components at the site in advance of the need. A warm
site is an offsite backup facility that is configured
partially with network connections and selected peripheral
equipment, such as disk and tape units, controllers and
CPUs, to operate an information processing facility. A
duplicate information processing facility is a dedicated,
self-developed recovery site that can back up critical
applications.

Is This Answer Correct ?    12 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

purchase orders issued to vendors have been authorized as per the authorization matrix

1088


WHICH OF THE FOLLOWING IS OFTEN AN ADVANTAGE OF USING PROTOTYPING GOR DYDTEM DVELOPMENT

2837