Answer Posted / shyam

bug life cycle:


1. New: When the bug is posted for the first time, its state
will be “NEW”. This means that the bug is not yet approved.
2. Open: After a tester has posted a bug, the lead of the
tester approves that the bug is genuine and he changes the
state as “OPEN”.
3. Assign: Once the lead changes the state as “OPEN”, he
assigns the bug to corresponding developer or developer
team. The state of the bug now is changed to “ASSIGN”.
4. Test: Once the developer fixes the bug, he has to assign
the bug to the testing team for next round of testing.
Before he releases the software with bug fixed, he changes
the state of bug to “TEST”. It specifies that the bug has
been fixed and is released to testing team.
5. Deferred: The bug, changed to deferred state means the
bug is expected to be fixed in next releases. The reasons
for changing the bug to this state have many factors. Some
of them are priority of the bug may be low, lack of time for
the release or the bug may not have major effect on the
software.
6. Rejected: If the developer feels that the bug is not
genuine, he rejects the bug. Then the state of the bug is
changed to “REJECTED”.
7. Duplicate: If the bug is repeated twice or the two bugs
mention the same concept of the bug, then one bug status is
changed to “DUPLICATE”.
8. Verified: Once the bug is fixed and the status is changed
to “TEST”, the tester tests the bug. If the bug is not
present in the software, he approves that the bug is fixed
and changes the status to “VERIFIED”.
9. Reopened: If the bug still exists even after the bug is
fixed by the developer, the tester changes the status to
“REOPENED”. The bug traverses the life cycle once again.
10. Closed: Once the bug is fixed, it is tested by the
tester. If the tester feels that the bug no longer exists in
the software, he changes the status of the bug to “CLOSED”.
This state means that the bug is fixed, tested and approved.

Is This Answer Correct ?    5 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is XML Testing? Do we have any tools to test the XML? Please let me know.

1577


What is the role of the test group vis-?is documentation, tech support, and so forth?

1613


Hi,all i have a desktop App. which have a feature, It's a demo version if u want full version then u have to perches it. Pls give me some idea ASAP how can i break the App.

1505


Tell me the SRS based review,brs based review

1691


How to do manual testing of a E-insurance project (end to end process)

2765






Hello everybody, How many people do you think one sprint team can have in average?

1269


Can you explain the pdca cycle and where testing fits in?

785


What type of questions will be asking for 2 years experience candidate in manual testing?

1800


Can you explain the elementary process?

655


What is an error?

671


What is manual testing and what is it process?

1047


Hi guys,I have 3+ years of exp in manual testing in a bangalore based MNC company.I Like to jump in chennai.So please if u know any jobs in chennai firms please let me know in my email-id. anbarasu2k@rediffmail.com. cheers, anbarasu.

1473


What is your approach when requirements change continuously?

719


What is your Approach when you find 10 Sev-1 bugs in 50 test cases?

2072


Do write a separate test case for regression testing? If it is yes, explain how to write the test case?

729