Answer Posted / shyam
bug life cycle:
1. New: When the bug is posted for the first time, its state
will be “NEW”. This means that the bug is not yet approved.
2. Open: After a tester has posted a bug, the lead of the
tester approves that the bug is genuine and he changes the
state as “OPEN”.
3. Assign: Once the lead changes the state as “OPEN”, he
assigns the bug to corresponding developer or developer
team. The state of the bug now is changed to “ASSIGN”.
4. Test: Once the developer fixes the bug, he has to assign
the bug to the testing team for next round of testing.
Before he releases the software with bug fixed, he changes
the state of bug to “TEST”. It specifies that the bug has
been fixed and is released to testing team.
5. Deferred: The bug, changed to deferred state means the
bug is expected to be fixed in next releases. The reasons
for changing the bug to this state have many factors. Some
of them are priority of the bug may be low, lack of time for
the release or the bug may not have major effect on the
software.
6. Rejected: If the developer feels that the bug is not
genuine, he rejects the bug. Then the state of the bug is
changed to “REJECTED”.
7. Duplicate: If the bug is repeated twice or the two bugs
mention the same concept of the bug, then one bug status is
changed to “DUPLICATE”.
8. Verified: Once the bug is fixed and the status is changed
to “TEST”, the tester tests the bug. If the bug is not
present in the software, he approves that the bug is fixed
and changes the status to “VERIFIED”.
9. Reopened: If the bug still exists even after the bug is
fixed by the developer, the tester changes the status to
“REOPENED”. The bug traverses the life cycle once again.
10. Closed: Once the bug is fixed, it is tested by the
tester. If the tester feels that the bug no longer exists in
the software, he changes the status of the bug to “CLOSED”.
This state means that the bug is fixed, tested and approved.
| Is This Answer Correct ? | 5 Yes | 1 No |
Post New Answer View All Answers
Login screen with Username, Password input fields,remember me check box,sign in and reset button write Test Cases for GUI, Funcitonal, Negative, Usability and Security testing.
how can u prepare the test plan?
iwant know IEEE formate ,how it is used and exactly where it is used? i have details it follows test plan, testcases...etc. i want real time explanation. pls any one give?
What is the most important phase in STLC and Why
how will you test transfer funds module...explain in detail
i want to for technical interview question paper along with in tesrviwe Phases i need
what is base time , how can we base time your doc"s ?
what is quality Factor
Have you worked in UDAP (Credit Card act 2009) project?What did you test in Billing & Payment modules?
What does entry and exit criteria mean in a project?
Hello again!! wanted to ask you HOW EXACTLY create stubs and driver in integration testing? 2.whats the difference between integration testing and system integration testing? Thanks!!
What is an entry criteria?
What kind of testing to be done in client server application and web application? Explain
what r the measure bugs found in your project??? Give some example abt this.
What do you understand by usability testing?