Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

what is entry criteria for intigration testing,,?
what is entry criteria for system testing?
what is exit criteria for intigration testing & system
testing??? plz give me proper examples ....
thanks & regards
svsekhar2003@gmail.com

Answer Posted / sreedevi

Entry Criteria for Integration Testing is "All Components
have Passed in Unit Testing".


Exit Criteria is "Test Suite Passes"

ntry Criteria: The conditions that must exist before a unit
of project work can commence.

Exit Criteria: The conditions that must exist before a unit
of project work can be deemed complete.



Entry Criteria for Unit testing phase are:

The following documents have been completed, reviewed and
approved:

1. Business Requirement Document complete

2. Program Required Documents complete

3. Preliminary Software Development Project Plan

4. Phase 1 Planning

5. Functional Specification

6. High-Level Design Specifications

7. Software Development Project Plan approved

8. Software Verification Plan approved

9. Software Configuration Management Plan

10. Quality Assurance Plan approved.



Exit criteria for the Unit testing phase are:

1. Unit test has been passed

2. The module resides in a baseline directory

3. The project is code-complete. There are no missing
features or media elements

4. All priority a bug have been fixed and closed

5. Internal documentation has been updated to reflect
the current state of the product. Note: Unit testing will be
performed mostly by the Developer.



Entry Criteria for Integration testing phase are:

1. The project is code-complete. There are no missing
features or media elements

2. The product satisfies the performance and memory
requirements specified by the Functional Spec.

3. Software/Curriculum have run and passed a Sanity
Test that has been provided by the QA group.

4. All priority a bug have been fixed and closed

5. Internal documentation has been updated to reflect
the current state of the product.

6. Curriculum has done a content review of the lessons.



Exit Criteria for Integration phase are:

1. The Integration engineer has tested for install
ability.

2. All priority a bug have been fixed and closed.

3. Internal documentation has been updated to reflect
the current state of the product.

4. The Technical Lead has submitted all files for
integration accompanied by Release Notes.



Entry Criteria for System testing phase are:

1. QA has spot tested content, features, and
functionality of the product and verified that it is
feature-complete.

2. The user interface and the feature set are frozen.

3. The final CD-ROM layout has been determined.

4. The Technical Lead has submitted all files for
integration accompanied by Release Notes.

5. The Integration engineer has tested for install
ability.

6. All priority a bug have been fixed and closed.

7. Internal documentation has been updated to reflect
the current state of the product. Exit Criteria for System
testing



The Exit Criteria for the System testing phase are:

1. Final Publications Draft of product publications,
including the Quick Start Guide, has been reviewed, tested
in QA, and approved by the Core Team.

2. All priority a bug have been fixed and closed.

3. The software runs on all the product’s supported
hardware and software configurations.

4. The product is compatible with third-party products
as specified in the Functional Spec. Final Entry Criteria



The Entry Criteria for the Final phase are

1. Quality Assurance Plan approved.

2. The work has been approved and signed off by
Product Marketing

3. Final Publications Draft of product publications,
including the Quick Start Guide, has been reviewed, tested
in QA, and approved by the Core Team.

4. All priority a bug have been fixed and closed.

5. The software runs on all the product’s supported
hardware and software configurations.

6. The product is compatible with third-party
products as specified in the Functional Spec.

Is This Answer Correct ?    3 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is bucket testing?

1161


what is the most critical bug u have to find in ur project.My application is ERP based,in this purchase module is there.plz tell me the answer?

2847


What is the difference between latent and masked defects?

1218


What is bug, deffect, issue, error?

1370


What is localization testing (l10n testing)?

1366


Hi.....wat r d major bugs we can find in banking domain???

2552


Hi ALl, Can you please list out Q & A for Test Lead,which Interviewer may ask in interview for Test Lead position

2020


What is Snapshot Testing? When we need to do and who will involve in this process and also what is the output document of this testing

2981


from where do u collect test data if u miss some data what will happen

2715


Why you are selected software testing as career ?

1426


what is e-tester?

2616


What is the test case?

1177


In simple steps how will you do unit testing using VSTS?

1382


can u merge 10GUI map files into a single GUI map file in winrunner?

2142


What is testing and maintenance?

1341