If I have one PO with me & I made GR with partial Qty &
after that I want to block PO for one month means user
shouldn't make GR against this PO & after one system should
allow to make GR. In this case where I need to do changes?
Answer Posted / dgdfhf
Open the Purchase Order:
Transaction Code: ME23N (Display Purchase Order) or ME22N (Change Purchase Order).
Navigate to the Delivery Tab:
Go to the "Delivery" tab in the Purchase Order screen.
Set the Delivery Completed Indicator:
In the "Delivery" tab, you will find the "Delivery Completed" field. Set this field to 'X' (checked) to block further Goods Receipt for the PO.
Save the Purchase Order:
Save the changes to the Purchase Order.
Monitor the Status:
Check the status of the Purchase Order to ensure that the "Delivery Completed" indicator is set.
Release the Block After One Month:
After one month, you will need to go back to the Purchase Order and unset the "Delivery Completed" indicator to allow Goods Receipt.
Open the Purchase Order:
Transaction Code: ME22N (Change Purchase Order).
Navigate to the Delivery Tab:
Go to the "Delivery" tab in the Purchase Order screen.
Unset the Delivery Completed Indicator:
Unset the "Delivery Completed" field (remove the 'X').
Save the Purchase Order:
Save the changes to the Purchase Order.
Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
Why do we use document types in sap?
What is goods movement? What type of documents is created after the goods movement?
What are the month end activities in sap mm?
Purchase group is assigned at to which organization element? Plant or purchase org or company.
How will you consider sub contracting po components which are not sent by your company to vendor but they are added by the vendor (sub contractor)?
What is the difference between external procurement and internal procurement?
How do we create consignment stocks?
What are the main features of consignment stock?
Why is sap so popular?
What is an rfq and how it is different from a quotation?
What is the difference between contract and scheduling agreement?
Why is negative stock needed in an organization?
What transaction code is used to convert planned orders (po) into requisitions in material requirement planning (mrp)?
What is the procedure to delete materials permanently from material master?
How do you check quota rating?