4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it?
Answer Posted / jegathish
Answer : 40 days
4m+6w=1/8.........(1)
3m+7w=1/10.......(2)
so the qus is,,,0m+10w=?
(1) x 3 --> 12m+18w=3/8 ........(3)
(2) x 4 --> 12m+28w=4/10 .......(4)
by solving equ (3) and (4), we get
10w=2/80 .............
so, 10w=1/40 which means 40 days
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
Explain the types of join supports by teradata?
How is polymorphism achieved?
Who invented data structure?
Why web api is better than wcf?
how you can rehearse the slide show timing in powerpoint 2013?
How does kubernetes provide high availability of applications in a cluster?
What is ex and vi?
What is css in coding?
What is the difference between datawarehousing and businessintelligence?
What is implicit polymorphism in hibernate?
What is cr keyboard?
Which protocols are supported by loadrunner?
Explain the bubble sort algorithm.
What is spring and hibernate framework?
What is the relationship between xaml and other transaction protocols? : xaml