Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

Your company manufactures small kitchen appliances. They are introducing a new product line of appliances in designer colors with distinctive features for kitchens in small spaces. These new products will be offered indefinitely starting with the spring catalog release. Which of the following is true?
A. This is a project because this new product line has never been manufactured and sold by this company before.
B. This is an ongoing operation because the company is in the business of manufacturing kitchen appliances. Introducing designer colors and features is simply a new twist on an existing process.
C. This is an ongoing operation because the new product line will be sold indefinitely. It's not temporary.
D. This is not a project or an ongoing operation. This is a new product introduction not affecting ongoing operations.

Answer Posted / vhin84

C

Is This Answer Correct ?    1 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Your project sponsor has requested a cost estimate for the project you're working on. This project is similar in scope to a project you worked on last year. She would like to get the cost estimates as soon as possible. Accuracy is not her primary concern right now. She needs a ball park figure by tomorrow. You decide to use: A. Analogous estimating techniques B. Bottom-up estimating techniques C. Parametric modeling techniques D. Computerized modeling techniques

1087


You are a project manager for Bluebird Technologies. Bluebird writes custom billing applications for several industries. A scope change has been requested. You know change is concerned with all of the following except: A. Managing change B. Verifying change C. Influencing causes of change D. Determining that a change occurred

1053


Your project involves the research and development of a new food additive. You’re ready to release the product to your customer when you discover that a minor reaction might occur in people with certain conditions. The reactions to date have been very minor, and no known long-lasting side effects have been noted. As project manager you should: A. Do nothing because the reactions are so minor that very few people will be affected. B. Inform the customer that you've discovered this condition and tell them you'll research it further to determine the impacts. C. Inform your customer that there is no problem with the additive release the product to them. D. Tell the customer you'll correct the reaction problems in the next batch but you'll release the first batch of product to them now to begin using.

1181


How to track your team members?

955


You are a project manager for Laredo Pioneer’s Traveling Rodeo Show. You're heading up a project to promote a new line of souvenirs to be sold at the shows. You're ready to write the scope statement, and you know it should contain which of the following? A. Project justification, benefit/cost analysis, project deliverables, and product analysis B. Product analysis, project product, and project deliverables C. Project justification, project product, project deliverables, and project objectives D. Product analysis, project deliverables, benefit/cost analysis, and project objectives

1271


As project manager, you know that all of the following are true concerning analogous estimating techniques except: A. It's a qualitatively based estimating technique. B. It's a top-down estimating technique. C. It's a tool and technique of Activity Duration Estimating and Cost Estimating. D. It’s a form of expert judgment.

1243


How do you set goals for your team?

961


What are the tools and techniques of the Contract Administration process? A. Contract change control system, payment system, payment requests B. Contract change control system, contract negotiations, payment system C. Contract change control system, contract negotiations, contract changes D. Contract change control system, performance reporting, payment system

994


You are a project manager for Uncle Sam's Flag Company. Your company has designed a new line of products featuring the American flag. Due to some unique circumstances, the products are in hot demand and the project sponsor has asked you to do whatever it takes to get this project completed early and make the products available. You are to add resources to the project. The sponsor agrees to pay the additional costs since time is now a critical factor. Which technique have you used? A. Crashing B. Resource leveling C. Fast tracking D. Resource loading

960


You are a project manager for Candy Works candy factory. Your project involves reporting information from the newly installed candy-counting machine to the financial system. This will give executives the ability to see production run counts at any rime during the day. The project sponsor has promised you a bonus if you get this project completed two weeks sooner than the scheduled project end date. The bonus will come in handy on your trip to the Bahamas planned for later this spring. You've got a few remaining project activities to wrap up before you can close out the project. Which of the following is the most appropriate response? A. You tell the sponsor the project is complete and treat the remaining activities as though they're problems that came up after project closure so that you can still get the bonus. B. You tell the sponsor the remaining activities are outside the scope of the project so the project really is completed and collect your bonus. C. You tell the sponsor the stakeholders added these requirements after the project was well under way and you never agreed to include them in the project so the project really is complete, and you collect your bonus. D. You tell the sponsor you aren't going to make the two-week early completion date as there are remaining activities to finish up.

1102


The grouping of project elements by deliverables is known as what? A. The code of accounts B. The work package C. The work breakdown structure D. The work breakdown dictionary

1052


You are working on a project and are in the Quality Planning process. You know that if the customer requirements are not satisfied while the product is still in the control of the organization, it may result in corrective action, rework, scrapping, and downtime. Which of the following is true regarding the cost of quality? A. Cost of quality is an output of this process, and this is an internal failure cost. B. Cost of quality is a tool and technique of this process, and this is a prevention cost. C. Cost of quality is an output of this process, and this is a prevention cost. D. Cost of quality is a tool and technique of this process, and this is an internal failure cost.

1026


Project managers have the highest level of authority and the most power in which type of organizational structure? A. Projectized B. Strong matrix C. Functional D. Balanced matrix

1140


What are the five project management process groups, in order? A. Initiation, Executing, Planning, Controlling, and Closing B. Initiation, Controlling, Planning, Executing, and Closing C. Initiation, Planning, Controlling, Executing, and Closing D. Initiation, Planning, Executing, Controlling, and Closing

935


You are a project manager for Star Light Strings. Star Light manufactures strings of lights for outdoor display. Their products range from simple light strings to elaborate lights with animal designs, bug designs, memorabilia, and so on. Your newest project requires a scope change. You have documented the characteristics of the product and its functionality using which of the following tools and techniques? A. Change control system B. Corrective action C. Configuration management D. Updates to the scope management plan

1119