how must steel will use for 1 cubic meter.formula of steel
for beam,column,lantern.
Answer Posted / mahi
mahi
Required steel in concrete is Depend on Types on concreting different structure
For Example,
R.c.c Slab = 0.5 to 1 % steel Required in volume of concrete
R.c.c Beam = 1.8 to 2% % steel Required in volume of concrete
R.c.c column = 2.5 % % steel Required in volume of concrete
R.c.c Road = 0.6 % % steel Required in volume of concrete
(1) Here take Column 1 m3 concrete volume calculation is
(2.5 x 1/100) x 7850 =196.25 kg steel Required
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
how many time use of plywood shuttering and IS code
what is directivity effect?
how will calculate 4"thick solid block quantities 1m3 sand cement ratio and breack up detail
how to calculate 1:5:8 ratio concrete cement, sand, metal and water please give me brief calculation
about higyway engineering
How we calculate the service time of buildings
how to calculate load for a bungalow and 1column carry how much load if the size of column ,9"*15" .....or total structure load......
what is difference between GTS bench mark and temporary bench mark
what are the layers of the national and heir aprox thickness??
what is the list of building construction equipment & teir output?
cause of cylinder test failure
why is the column design?
how to calculate the concrete mix m30 by volume
For making a new road in a village having a school & hospital , tell the steps of construction systemically ?
all technical question