how must steel will use for 1 cubic meter.formula of steel
for beam,column,lantern.
Answer Posted / mahi
mahi
Required steel in concrete is Depend on Types on concreting different structure
For Example,
R.c.c Slab = 0.5 to 1 % steel Required in volume of concrete
R.c.c Beam = 1.8 to 2% % steel Required in volume of concrete
R.c.c column = 2.5 % % steel Required in volume of concrete
R.c.c Road = 0.6 % % steel Required in volume of concrete
(1) Here take Column 1 m3 concrete volume calculation is
(2.5 x 1/100) x 7850 =196.25 kg steel Required
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
Which are the top apps for you civil engineering?
How to construct a water sump in a rocky soil?
at which depth the construction of tunnel is economical from cost and engineering aspect.
How many Sft of Level Plaster per Kg
I need Bhel engineertrainy test papers in civil engineering please send to email id - hisandy66@gmail.com
What are the applications of cad?
Which brick is best for construction ,either fly ash or AAC BLOCKS
How to calculate or what is the process of calculation for making 1Metre squre area by AAC Blok which quantity of Cement, Sand & Chips are to be required?
What is the substitute of Mastic Asphalt?
how much area can be platered by a mason for exterior
how to estimate material requirement for an area of house in square feet?
Can anyone suggest how to determine scheduling of reinforcement of floor beams from Staad model,other than clicking each beam respectively 7 noting down the values ?
what is the amount of absorption of slurry in shuttering ply board. what is the amount of slurry leakage allowed for 1 m3 of concrete.
Define What is rigging?
if dia of inner circle is 42 m and depth is 1.5 m and width is 1 m ,then whait is the quantity of steel?