how many hacking to be made in one sqft for concrete surface
before plastering as per the IS Code

Answer Posted / chalapathi raja kmv ltd

35 to 45 nos per one sq ft
3mm depth
5cm c/c

Is This Answer Correct ?    2 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

can you give me the details of rate analysis of steel and concrete?

2479


Thumb rule for steel qty for 1m2 in kg/m2 column slab footing beam

5143


in staad pro. modelling for a parallel scissors chord truss, when i assigned roller support i.e fixwd but with all Fx, FZ, Mx, My and Mz release except Fy... the analysis results " in stability at a joint, with direction Mx or My..what could be the reason...anyone please explaing

3357


Dear Sir I Mahesh C. Bhamre have already given a Exam for Superintendent Officer / Public relation Officer Exam Dharmday Aaukta held at Nashik on Date 29/08/2010. My seat no was 5040247. and my cell no is 9822677994. and my mail Id is - mahesh.bhamre@rediffmail.com So can you pl send me details of result of respective exams. Thanking you in Anticipation.

1835


The properties of concrete HA-30 and how does it differ with M 30 (specify the important characteristics like workability,strength,mix design,slump test value)and what is the standard relating to it

5570






what is tension footing?

1547


What is the use of offset command?

692


Rate analysis for construction of a solid block masonary of size 400x200x200 in C.M.1:5 in superstructure .Compressive strength 5.00 N/Sq.mm Confirming to IS: 12894:1990, with necessary scaffolding, raking of joints and pointing the same. I require rate per Cum.

2002


Why the statue of liberty is made of copper?

671


1.How much batten required for 1 sqm Shuttering. 2.how much pipe & clamps required for staging of 100 sqm shuttering at 5.0 m height.

1811


can any one explain bar bending schedule of bems and columns and slabs ??

1428


If density of cement is 1500 Kg/m3, the how is specific gravity 3.15 ? (Density of water is 1000 Kg/m3)

1921


how to caliculate required amount of cement and sand required for 1cu.m.

1752


PL.tell me about civil engineering questions with answer

2130


why we can use dust in concrete insted of fly ash

1705