why we do multiply 1.54 for dry volume of concrete?
Answer Posted / ramya
If wet volume is converted into dry volume then dry volume is raised 54% of wet volume
Hence, dry volume : Wet volume➕ 54%wet
. volume
dry volume : ( 1➕ 0.54 ) wet volume
. dry volume : 1.54 * wet volume
| Is This Answer Correct ? | 9 Yes | 1 No |
Post New Answer View All Answers
how much used soil in 1 brick of standard size?
how to find the cement bags and sand requirements for the one square meter of internal,external,ceiling plastering by using the various ratios like 1:3,1:4,1:5,1:6
IS code for Rolling Margin of steel
what is labour consume factor in residential projects
how to calculate the concrete mix m30 by volume
what are the proper pipes for salt water line
Define a polyline?
what is the painting co efficient of slope roof tiles?
how many spacers we need for 1 ton reinforcement? aprox.
TELL ME THE EQUATION FOR OGEE SPILLWAY
Define polar co ordinates.
Actually i am confused that how to calculate the bending moment for a semi-circular beam and curved slab.If any one have a good idea about the matter,please give the answer with a suitable example. Thank you......
indian standard split spoon sampler
what is the formula to find the sttel (bar)length in beam having bent up at l/4 t 45 degree & 60 degree.
How to arrive d*d/162 , for finding the kg per meter , wt of steel