what is the shuttering normal clear cover for footings,
walls, beams & columnms
Answer Posted / shalya
Footing 50mm
Column 40mm
Beam 25mm
Slab 25 ,20mm
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
Explain how you can use different dimension tools in CAD? What are the different dimensions available?
Does VDF add strength to the flooring apart from preventing water ingress?
how to take concrete quantity for precast segment for viaduct project?
how to calculate the mortar for 10'*10' size room for both plastering and for masonry work?
can i get civil engineering test papers.......?????
if dia of slab beam bar is38mm what its clear cover any method of provide clear cover
How to calculate ventonite bag in pile ( pile depth 25 m dia 1m)
1) a)to prepare mortar for bricklaying how much amount of water should be added for its maximum strength and workability(to avoid cracks which results, when high quantity of water is added)?is their a formula or ratio? b) suppose we want to make 1:3 mortar,what is the best way to measure cement ,sand and water and how? c)time before which freshly prepared mortar should be used? d)proper way to mix and make mortar? e)when should curing start after laying bricks and for how long?and also how many hours per day? f)what is shear wall (please in terms of layman lol) bookish definisions are confusing.... g) and last,acc to codes what are max no. of course that should be laid in a day.
Minimum and maximum size of the building components
Types of column foundation and how to calculate its steel quantity.
is there any influence of water(used for mixing of concrete) on a weight of harndend concrete.
What is binding spacing of the rebars at lapping zones.
Wats the formula of eccentric footing and how was calculated from concrete qty
how to calculate mivan shuttering matrial
The internal dimensions of a wire house 15m*5.6m and the maximum height of piles is 2.70m. What is the maximum number of bags to be stored in two piles ?