What is the quantit;(pratical
method) of cement,
sand, and gravel to be used in
M25 grade of concrete for
1000 x 1000 x 1000 mm of
sand (for cement please
mention in kilos, and for sand
and gravel please mention in
cuft
Answer Posted / raju goyal
Basically M25 is the design mix grade. So we don't know what is the proportion of mix.
As per thumb rule it's 1cement:1sand :2 aggregate. For dry quantity it's 135% more of it's casted quantity.
Therefore dry material quantity will be found as given below formula of 1 Cum.
1 Cement = (1.35÷sum of proportion) e.i.
1. Cement =(1.35÷4)=0.3375 Cum or 10 bags
2. Sand. = 0.3375×1=0.3375 Cum
3. Aggregate=0.3375 ×2=0.675 Cum.
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
What is the difference between Rock And Murrum. How to claim that excavated material is not a murrum but rock.
what is the clear cover for shearwall?
how to find ssm in foundation?
Permissible wastage of cement as per IS code ? In which IS code I get it?
A rock anchor 3 1/2” in diameter is placed in rock. The which has an allowable shear strength of 1200 psi. Determine the required anchorage length to safely carry a 80 ton load using a 2.0:1 F.S
For what purpose bedding is used under storm water drains?
What is the meaning of Brick- M 35 grade? Is it a common brick or it's a concrete brick?
how to calculate Rate of analysis for 100 m3 Any ratio of concrete ? including labour
I Want To Know Quantity of Cement Conc. & Sand in Column of 9"x9"x10'
what does the track parameter mean in staad.pro?
what is mc arther pile?
TELL ME THE EQUATION FOR OGEE SPILLWAY
Explain moment of inertia?
Suggest how many column, beem, etc required for 30 mtrs x 21 mtrs width x 8mtrs height for industrial shed of ground floor. I want to know the quantity of tmt steel consumption and Concrete consumption for budgeting
how we calculate the vol.of wet concrete..?